They seem to (finally) be finishing off the granite flooring in the York Street moat area at the moment.
They are pouring new concrete outside the Bay Street doors that lead to Scotia Bank Arena.
The escalators etc in the SBA leading to new GO Bus area and the area surrounding them appear to be finished, I think they may, at least, open those doors again next week, once the concrete noted above, is done. I assume escalators will remain closed until the new GO BUs terminal opens. (Soon??)
They are continuing to work on Platform 3 of Union Station and appear to have installed new doors leading from it to the Bay Concourse. Still working on the outside of the walkway that goes across Bay Street to the current GO Bus Station.
They are working again on installing granite tiles in the Bay Street Moat.
They appear to be tidying up the walkway that goes from the Front East to Front West moats (below the Plaza); maybe it will re-open soon?
They are working on the ceiling above the new stairs that go to Bay Concourse from below the ramp that leads to the VIA concourse. They have hung the second refurbished lamp on the south side of this ramp area (still need to do the 2nd one on north side.)
They have walled off entry from the Great Hall into the east building so that one can no longer look down into the Bay Concourse. escalators - not sure why except that the ground floor of the east wing is unoccupied.