Isn't the transitway discontinuous between Erin Mills and City Center? I know they're planning on eventually building a connector between the two halves, however we have very little info about how that would get built (likely as a City Center Tunnel), and in that case they could easily run the missing part south of the 403, and at that point you'll have a station that's 300m north of the northern end of the platform. Certainly not a great transfer by any means, but also not the end of the world.
yes it is due to lack of funds as well opposition from the NIMBY folks along with the retirement home at Mississauga Rd.

The plan was to have the the ROW west of Duke of York with a Duke of York bridge over the 403 to it. It was to be part of the north service road from Hurontario to Creditview. No clue if this plan still exist at this time.
 
Update:
Rathburn was a warzone Sat with it close between Station Gate to Duke of York for everyone.

No work has taken place on the south pier support since I last shot it, but core drilling for caisson taking place at the intersection in the north-east conner.

Wet Utilities Completed to Date ✔
Watermain - 6.1 Km of pipe installed to date ✔
Storm - 3.3 Km of pipe installed to date ✔
Sanitary - 1.7 Km of pipe installed to date ✔
Total of all wet utilities is 11.5 Kms Dry Utilities Completed to Date ✔
88 Hydro poles installed ✔
5.06 Km of concrete encased underground hydro duct banks installed ✔
6.12 Km of underground hydro cable installed ✔
30.81 Km of aerial conductor installed

Work is to get underway this month for the guideway
Guideway construction in preparation for track installation along Hurontario Street will progress from south to north, beginning between Matheson Boulevard and Britannia Road.

Construction will occur in the mid-block sections (the areas between intersections) with minimal/no impact to pedestrians and traffic flows at intersections for this stage of work.

Work will occur in all of the mid-block zones simultaneously and will take approximately four months to complete in this area.

Once the guideway is constructed, the configuration in the centre of the roadway will be permanent, prohibiting U-turns and left-turns across the tracks at undesignated locations

QEW Push Box
The box will be built on the north side of the North Service off the road. Come Thanksgiving this year, the box will be push onto the road and then south to the QEW overpass. Talks still on going with MTO about closure and no final plan at this time.

Brampton South
● Tree protections
● Staging on both sides of Hurontario Street between Bartley Bull Parkway and Brampton City Limits are expected to begin by the end of March
● Wet Utilities set to begin once traffic staging is complete (watermain, sanitary and storm)
● Installation of guideway, tracks, and OCS poles at the OMSF are ongoing, and connecting guideway infrastructure onto Edwards Boulevard
● Electrical connections and the overhead steel platforms are being installed at the OMSF building Mississauga South

Mississauga South
● Sanitary structure installations will continue along the east side of Hurontario until the end of March
● Hydro Pole, aerial cable works, and duct banks continue along Hurontario
● Alectra relocation are progressing north of Mineola Road towards the QEW
● Site preparation, including clearing and grubbing of vegetation and sidewalk demolition, set to occur near the QEW in advance of the Push Box activities later this year
● Work continues at Mary Fix Creek to expand and revitalize the creek bed
● Work continues at the Lakeshore West Push Box with the construction of a temporary bridge in advance of the underpass installation

Mississauga North
● Storm and watermain installations continue between Eglinton Avenue and Matheson Boulevard as well as between Derry Road and Topflight Drive
● Alectra relocations, road widening, and new curb installations continue between Matheson Road and HWY 401 as well as along Britannia Road, including the installation of transformers and switchgear
● Road widening between Matheson to HWY 407 continues with excavation and the installation of subdrains
● Installation of permanent street light installations continue between Matheson Road and Britannia Road as well as between Derry Road to HWY 407
 
March 21
There will be very few pier supports as they will be a few 100' apart to support the elevated section.

The eastbound off ramp from the 403 to Hurontario is been shift north to line up with Sherwoodtowne Blvd Dr intersection for better connection
51958186085_58ff8855e3_b.jpg

51956613952_18a5454641_b.jpg

51957898214_24f60a57e6_b.jpg

51957600441_d7c24c5188_b.jpg

51958186300_b25b272cb0_b.jpg

51956614432_506939382b_b.jpg

51957898694_ba1c3d0e76_b.jpg

51957663618_8a4b86ec90_b.jpg

51957898774_efd6ce297f_b.jpg

51958186850_c15228647d_b.jpg

51957601276_c426bd1cd3_b.jpg

51957601326_2a54f4fb57_b.jpg

51957601361_cd0c514b4f_b.jpg
 
March 21
There will be very few pier supports as they will be a few 100' apart to support the elevated section.

The eastbound off ramp from the 403 to Hurontario is been shift north to line up with Sherwoodtowne Blvd Dr intersection for better connection
51958186085_58ff8855e3_b.jpg

51956613952_18a5454641_b.jpg

51957898214_24f60a57e6_b.jpg

51957600441_d7c24c5188_b.jpg

51958186300_b25b272cb0_b.jpg

51956614432_506939382b_b.jpg

51957898694_ba1c3d0e76_b.jpg

51957663618_8a4b86ec90_b.jpg

51957898774_efd6ce297f_b.jpg

51958186850_c15228647d_b.jpg

51957601276_c426bd1cd3_b.jpg

51957601326_2a54f4fb57_b.jpg

51957601361_cd0c514b4f_b.jpg
One thing I have not seen in the planning documents is how the LRVs will transfer from the at-grade centre of Hurontario onto the guideway. Will they cross Hurontario at-grade to get to the guideway or will the guideway rise in the centre median and then fly over Hurontario? I really hope it is the latter.
 
One thing I have not seen in the planning documents is how the LRVs will transfer from the at-grade centre of Hurontario onto the guideway. Will they cross Hurontario at-grade to get to the guideway or will the guideway rise in the centre median and then fly over Hurontario? I really hope it is the latter.
I have yet to get an answer on that issue and would be a mistake not keeping it elevate to the north centre and then ramp it. The south will be at grade crossing both Sq One Dr and Hurontario. This will be an issue in time.
 
I have yet to get an answer on that issue and would be a mistake not keeping it elevate to the north centre and then ramp it. The south will be at grade crossing both Sq One Dr and Hurontario. This will be an issue in time.
Thanks for the reply! I really hope it is ramped in the median.
 
Thanks for the reply! I really hope it is ramped in the median.
There is more than enough room to do it on the north side, but next to none on the south side
 
Reduced Lakeshore West service on April 3 and 10:
· GO buses will replace most trains on the Lakeshore West line on Sunday, April 3 and 10 to carry out important work for the Hurontario LRT project that can only be completed when trains aren’t running.
 


@TOareaFan has passed away. He was very active here for many years and posted 11,927 messages. He joined UT in 2008. This seemed like the most appropriate thread to post this update.

We certainly agreed to disagree on a few topics, such as the HuLRT/HMLRT where he was more in favour of BRT as the technology, but I always enjoyed the conversations. He was very passionate about Brampton getting weekend GO train service.
 
Port Credit GO – Check departure boards before boarding​
Port Credit GO customers: Due to important construction work, trains may depart from a different track than usual this week between 9 a.m. and 3:30 p.m. and 8 p.m. until the end of service. Always remember to check departure boards before boarding. You can also check GO Tracker before your train’s scheduled departure time for real-time track information. We appreciate your patience.​
 


@TOareaFan has passed away. He was very active here for many years and posted 11,927 messages. He joined UT in 2008. This seemed like the most appropriate thread to post this update.

We certainly agreed to disagree on a few topics, such as the HuLRT/HMLRT where he was more in favour of BRT as the technology, but I always enjoyed the conversations. He was very passionate about Brampton getting weekend GO train service.


The MP mentions his twitter handle of TOAreaFan, but as we know he used the same one here. His passion for Brampton is mentioned and we definitely saw that in his posts in this thread, and several others.
 
Match 30
Drove the route today and very little going on in Bampton. The construction lights are finally being install at the 403 westbound off ramp and maybe working by the end of the day. Police on hand to deal with lack of traffic signals once change over take place as well string wires.

The east sidewalk is being rebuilt for the underpass at Port Credit. New tall hydro poles installed on the east side up to Mineola Dr with crews preparing to string new wires.

80% of the embankment on the west side has been removed for the Mary Fix Creek work as well the tunnel section.

The only thing I saw at PC for the tunnel was some shoring installed between the tracks and no work going on.

Both elevators were out of service with crews working on them.

GO Trains using platform 2 & 3

A rough built road in place for the LRT tracks to/from the GO 407 Bus Station and the Maintenance Complex. This will be upgraded later this year for both a road and the guideway. No photos.

Centre lanes are block off 100% between intersection to allow the building of the guideway from Matheson to Britannia.

Most of the east side curds are in place north of the 401 with section to be pour. Once pour, the northbound lanes will be pave to shift the traffic to it to allow the centre area block off for building the guideway.

More up on site.
51972501730_185945cd00_b.jpg

51972501580_9421c64e62_b.jpg

51971937796_002d42aa91_b.jpg

51972228054_2bb678c26d_b.jpg

51972007583_e779f53bdf_b.jpg

51971937381_83078f9c8c_b.jpg

51972007333_67ab312092_b.jpg

51972227459_fd4f6038ae_b.jpg

51972006993_1699e78cac_b.jpg

51972500485_e21b0e6744_b.jpg

51972006743_5021797ebe_b.jpg

51972006413_ee49f7c97c_b.jpg

51971936326_874b1d473a_b.jpg

51972499805_d34f2eeabe_b.jpg

51971936026_6ce689833e_b.jpg
 
Along Rathburn Road, lots of construction occurring today. Eastbound lanes were closed off. Photos below.

Progress is being made on the 403 LRT bridge too, with lots of piles of dirt and form work occurring. Lots of earth works occurring at the QEW for the new underpass. Couldn’t grab pictures of these last two items sadly.

BF80075B-883C-4632-B625-47F7F99A05AC.jpeg
D66CFE0C-61CB-4419-9C44-5A798886A90A.jpeg
A6B9AAA2-878C-41DC-AAA5-0057AAB4E179.jpeg
 

Back
Top