Likely they have an automated date field in the PowerPoint version and they converted it to PDF todayMetrolinx has a picture dated today (Dec 24, 2025) in one of their slides? Seriously? That quick a turnaround?
Expect 6 months delay from this timeline due to Queen station shafts design is currently being revised. There might be a pause of excavation at this station once it reaches bottom of piles (bedrock level).
design changes this late?Expect 6 months delay from this timeline due to Queen station shafts design is currently being revised. There might be a pause of excavation at this station once it reaches bottom of piles (bedrock level).
There will be one shift once the first half of the bridge is complete, slated for end of January. There is more room to the West outside the frame of the last photo.^Will the Don bridge be shifted incrementally as they run out of space at the west end - or will it be a single shift all the way eastwards when more is completed?
From the shots to date, it appears they are running out of working room on the west end - is the theory that the crane is effectively fixed so all the assembly happens in one work station, and the bridge moves as it grows? It will be getting heavier and more to move as each linear section is added.
I'm sure there is a reason why they didn't start fabricatiing with the east end in its eventual position, or at least closer to it - wondering what that reason is.
- Paul
They need to cut and cover so they can do the TBM extraction for the Pape tunnel TBMsCut and cover on the portal? Boo. So undramatic. I wanted a hole to just appear out of the middle of the hillside. Oh well.