kotsy
Senior Member
And here it is being lowered into position. Quality not so great due to very windy conditions.
Only the first TBM so far.are both onsite, or are we waiting for one
Video here on LinkedIn by the Minister of the lowering of that piece pictured.And here it is being lowered into position. Quality not so great due to very windy conditions.
View attachment 717002
View attachment 717001
Righty tighty lefty loosey makes me think it will turn clockwise if you're standing behind the TBM or anticlockwise if you're facing itOK, this may be the nerdiest question of the day, but I will ask....does it turn clockwise or anticlockwise ?
I'll be darned if I can figure that out by looking at it.
- Paul
BOTH!OK, this may be the nerdiest question of the day, but I will ask....does it turn clockwise or anticlockwise ?
I'll be darned if I can figure that out by looking at it.
- Paul
BOTH!
The cutter head will rotate in alternating directions to dislodge soil and rock that gets carried out the back on a conveyer while the TBM pushes itself against the precast concrete sections to move it forward and compact the tunnel built behind it.
Thank you, that's very interesting. So the motion is more like a reciprocating scraping than an auger or corkscrew rotation..... who knew?
Paul
The cutterhead as shown is dressed with a number of disc cutters (for scoring and breaking rock) and rippers (for scraping soft ground and fragments of rock). The material accumulates behind the cutterhead, filling the bottom of the cavity as the screw conveyor removes the material.If you look at the cutting head, the cutting parts look symmetrical. That's because it's meant to break rock and soil in either direction. It will turn clockwise for a period, then counter clockwise and continue for a while. This is to even out wear and break any stubborn rock that didn't break in one direction but will in the other. The spoils go through the openings in the cutting head and fall on a conveyer which takes it through the back where workers load rail cars to the Exhibition site where the spoil is added to muck pits.
I found out recently that unlike the Yonge and Bloor-Danforth subways which created the Leslie Spit and filled in Trinity Bellwoods Park's ravine, the Ontario Line's spoil will be distributed to construction projects across the country and beyond. I would have liked it to fill out Leslie Spit a bit more and possibly extend it out into the lake but there are different environmental considerations than there were in the 50s.
Now that Metrolinx has given up on the 2031 projection, we get an insight into why. They’ve given us their first official “guess” at how long an underground station will take to build: 3 years.
Construction of Queen-Spadina station will begin in March until “early 2029”.
If completion in early 2029 actually means the station is substantially complete and more or less ready for service then 2031 is not out of the question assuming 18-24 months for testing and commissioning. Though I do think it's likely major delays will be at Yonge and Queen and not here.
So 2041 opening is not much a joke after all...That's just Queen-Spadina station, others are behind. I was told Osgoode is just 2 months behind schedule but Queen Station (at Yonge) seems to be at least a year, if not two years behind. After they closed Queen Street in 2023, the site sat inactive for about 2 years before they started excavation. Issues were discovered and they had to redesign the station. Excavation at Queen is now expected to be concluded end of Summer with construction of the station starting Fall 2026 at the earliest. Add 4-5 years to that to build an interchange station that is far more complex than Queen-Spadina and you're into the 2030s before they can start testing a completed line and fixing deficiencies.