Part 2
March 27
Still no work done on the east QEW bridge support that started sone months ago.
Odd they stop digging the south of Pinetree and did not bring it up to the intersection like Pinewood. There is a driveway between Pinetree and Pinewood to allow the small number of residents from a small cul-de-sac on the westside to make a left turn. Most likely not able to make an U-turn at Pinewood since the left turn southbound is on an angle.
At least 60% of the guideway between Pinewood and Mineola is ready to have the concrete base pour starting March 30 as all underground work is done with final backfilling taking place. It will be about mid April for the remaining section is ready for concrete. All the guideway curb for PC has been poured and the road paved beside it.
The guideway south of Mineola only needs a small amount of concrete poured for the centre curds and it will be 100% complete and waiting track work. The base of the station is poured as well
Part of the westside guideway is dug where it will move to the centre of the road with the base of the guideway poured except a section at Englewood that was ready for it in 2025. Based on how the road curb is poured south of the switching sides, the shifting of the southbound lane will start just south of the north end of the barrier wall with a section of the base is poured.
The northbound curb from Englewood to the north end of the plaza has been poured and road pave. As it stands, there will be three lanes with a single lane of traffic in both direction from the north of the road shifting to the south side of Englewood where the guideway leaves the road. The centre lane will be use for left turning only.
No change south of Englewood for the guideway and sidewalk since 2025
Crew working in the centre of Hurontario St for hydro work from the substation.
Saw no new work for the south entrance but the south end of the south entrance is trap and looks like brick work maybe taking place.
There were not fooling around with the guideway work north of Mineola since the end of February that any lost time due to weather has been made up or is off a few weeks at this time
The width of the Mary Fix Creek to the New spillway as well how deep it is below the base of it that any flooding at the south end is non existing in a 100 year flood.
Only enough room for three lanes for the plaza area
Where the southbound lane shift to the left
Station Platform ready to be built and track work to take place
Guideway ready for the base to be pour
Where the digging of the guideway stopping too short of Pinetree