Tim MacDonald
Senior Member
Part two - South of the QEW
Thanks and shows a few things clearly than the ground level.Part two - South of the QEW
View attachment 728548
View attachment 728549
View attachment 728552
View attachment 728550
View attachment 728551
View attachment 728553
View attachment 728555
View attachment 728556
View attachment 728557
View attachment 728558
View attachment 728559
View attachment 728560
If you had waited a day, you'd see that The Paisley / Hurontario inetersection will actually be closed tomorrow at 10PM to May 18th at 10PM for guideway / track work within the intersection.The first shot is as far north as I flew today which is just north of Paisley.
Nothing for trackwork a week ago for Bronte being lay but tracks in place from the Queensway to Paisley with tracks pour up to the first haft of the fire station driveway. The remaining section on both side of Paisley will be done once Paisley intersection is done. Paisley was supposed to be done in 2025 before King St and close to a year late.If you had waited a day, you'd see that The Paisley / Hurontario inetersection will actually be closed tomorrow at 10PM to May 18th at 10PM for guideway / track work within the intersection.
View attachment 728589
Ray Lawson / Hurontario has some more storm drain work that needs to be completed before they can shift the remaining lanes over. It'll be happening from April 10th to April 20th and will occur in three phases to keep traffic moving.
View attachment 728590
Has anyone been around Bronte College / Hurontario to see the progress on the track installation there?
From the notice:Hard to tell from the map if Ray Lawson work will be done in phases for the storm drain work or full closure for northbound traffic. Wouldn't be surprise guideway work will start for that intersection once the storm drain work is done in two phases.
When will this thing open again? This thread is 20 years old.
The original planned opening was like what, 2022? This is worse than Eglinton.My Guess would be sometime in 2032 or 2033
It definitely goes without saying. I was patient when they finished the work over the 407, and I was patient when I started hearing about the guideway being built in Brampton. I remain hopeful that the project will be finished soon, but know that I can't be let down any further than I have already been by people speculating that this would have been done in October of 2024. We'll see what the future brings.In fact, there is still a lot of work to complete. Patience is needed.
I said something similar and was told that these lines are the first of their kind (whatever that means) here, so whatever lessons they've learned will be carried forward on new projects, not the current projects they're working on. However, I'm so over LRT's at this point. I would much rather see a dedicated bus lane down a busy road during rush hour traffic instead of another who knows how many years of LRT construction.I would hope the builders have learned from those other lines, and commissioning ought to be much more organized and straightforward. So hopefully time gained on the back end. But still timewise it will be a while yet. But it's good to see lots getting done.
When will this thing open again? This thread is 20 years old.
It's a good thing that Metrolink has all of these Alstom trains, like the ones for line 6 in storage for this lineMy Guess would be sometime in 2032 or 2033
That was when the line was proposed that was follow by a land use and an EA for the line. As far as I am concern based on my background and seeing the corridor first hand, The line will open by the end of 2028 or early n 2028 unless something happens over the next 12 months, Contract was awarded 2019 with construction starting 2020.When will this thing open again? This thread is 20 years old.
It was scheduled to open September 2024 in 2019 and was pushed back to December 2024 after the contact was awarded.The original planned opening was like what, 2022? This is worse than Eglinton.
One thing I learned from Line 5 and 6 construction is that at the point where the row seems to be coming together - which this line now is at, the "sea of mud" stage is mostly over - the observer begins to think " just a few more things to finish - why is it going so slow?". In fact, there is still a lot of work to complete. Patience is needed.
I would hope the builders have learned from those other lines, and commissioning ought to be much more organized and straightforward. So hopefully time gained on the back end. But still timewise it will be a while yet. But it's good to see lots getting done.
- Paul
There were a few LRV's in the yard last year and was told the rest were inside but not sure how true if that was correct. February 2026 saw 4 LRV's way at the west end or was it 6 as it was very hard to count them. There are currently 16 LRV's in the yard based on a photo shot from a plan over the yard. How many maybe in the carhouse is unknown, but there are supposed 27 in total for Phase 1 and 44 once all extensions are built.It's a good thing that Metrolink has all of these Alstom trains, like the ones for line 6 in storage for this line