Dec 28

Testing Testing
45804461114_d8bd542645_h.jpg
 
March 22

Coming down soon
46762940984_02d39d557c_h.jpg


46762936764_e3064c8ebc_h.jpg


32544336597_8a46e3156b_k.jpg



Soil Modification - Micro Piles - to shore up the foundation of the one building that will remain.
32544334217_0c6d9b2f8b_k.jpg


40520272443_af7723e6ba_k.jpg
 
March 29

46590581275_3c7b230b76_k.jpg


Still standing
47506027491_f28b7c7fee_k.jpg

40540070973_4bf5ea44e5_b.jpg
47506025721_9b3567713b_b.jpg
40540070153_caa1f80918_b.jpg


All shored up - will stay standing.
47506024451_078f94e254_k.jpg


Wrecking Ball
47506021871_cce3566a80_k.jpg


40540068893_7fa266116b_k.jpg


Waiting for the new neighbors
46782290254_a881969540_k.jpg
 
April 9

46680576905_94dd593b1f_h.jpg


April 11

32653738197_44233f576a_h.jpg


Getting ready to put in a secant wall - directly next to a subway line. They are preparing the forms for pouring a guide.
33719183738_ca9d189789_h.jpg
 
April 16

46723860365_837a022581_h.jpg


32697005407_242113e0ed_h.jpg


Brand new and VERY yellow.
47586763592_2dcb2bc799_k.jpg


Secant tubes - one on the left has teeth on the bottom the others cant be bolted on as it goes deeper.
40672970773_6c06909303_k.jpg


Some assembly required
47586762752_56a380b536_k.jpg


40672969973_5bc5ff034c_b.jpg
47586762122_7c88e78147_b.jpg
One of those things you don't think of - tieing down the styrofoam forms so they don't float up when the form is filled with concrete.
 
April 22

almost there

47682280891_6282915033_h.jpg


All the way from Belvidere
40715998793_53ffe3f626_k.jpg


Things that go in Secant's ( Beams - Cages - Workers )
40715996913_51ca7c5862_k.jpg


Measure twice - drill once - measure again.
46766157495_9772b765b3_h.jpg
 
April 26

Overlap
32774054687_c1674f1fb1_h.jpg


Sleeve
33840185748_b278f6feaa_h.jpg


32774056817_fbda0e4cc8_h.jpg


Haven't seen these plates and dogs in action - possibly holds up the bottom sections of a sleeve while the top ones are unbolted and moved aside ?
33840183818_55704662a6_h.jpg
 

Back
Top