Rezoning times can vary from 90 to 160+ days for complex applications.
A good primer of the Edmonton Design Committee. In addition, general requirements of a submission. Presentations occur at the rezoning and development permit stage.
More information can be found on the city's Development Process page or by watching this video:
The development permit stage may include Environment Impact Assessments (there are multiple phases/types depending on whether remediation is required), Traffic Impact Assessments, and Parking Impact Assessment.
Building permit stage - ever wonder why construction sometimes hits a snag or delay? This is probably why. Safety code inspections take place throughout the building process.
Compiled information from the City of Edmonton.