Construction Staging Area - 2442-2454 Bloor Street West and 1-9 Riverview Gardens (Phase 1 and 2)
Major construction activities and associated timelines for the development are described below:
• Demolition: January 2021 to September 2021
• Excavation and shoring: September 2021 to December 2022;
• Below grade formwork: January 2023 to January 2024;
• Above grade formwork: February 2024 to September 2025;
• Building envelope phase: September 2025 to March 2026; and
• Interior finishes stage: September 2025 to September 2026.
The construction staging area for Phase 1 and Phase 2 will be set up within the first public laneway north of Bloor Street West, east of Riverview Gardens, for a period of 24 months. Additional requirements for Phase 3 will be discussed in a future report.