Could the opening date be announced in June for the September opening date??hoping that this latest software patch is the final one...
|
|
|
Could the opening date be announced in June for the September opening date??hoping that this latest software patch is the final one...
Could the opening date be announced in June for the September opening date??
0% chance this is opening in September, sorry to break the news to you.Could the opening date be announced in June for the September opening date??
I still do not understand why they can't "half open" part of the line, while still fixing those small parts where the problem remains.0% chance this is opening in September, sorry to break the news to you.
If anything that might take even longer - systems are so integrated that it would be very difficult to do this. Also, the "remaining complications" are relatively minor, we can wait.I still do not understand why they can't "half open" part of the line, while still fixing those small parts where the problem remains.
Surely the remaining complications are only in select locations, and not applied to the whole line...???
Sorry, not trying to rant, just frustrated like everyone else waiting...and waiting...
its because of how dumb the contract was written.I still do not understand why they can't "half open" part of the line, while still fixing those small parts where the problem remains.
Surely the remaining complications are only in select locations, and not applied to the whole line...???
Sorry, not trying to rant, just frustrated like everyone else waiting...and waiting...
In Seattle they're partially opened their new line and I only saw journalism about how "the line is finally open"All the reasons above, and the most behind station is Eglinton/Yonge, which is kinda the most important station in the system.
Another reason is when you do partial opens it leaves opportunities for journalists to say its a failure, etc because its slow etc (might not operationally be able to run smoothly with partial open) and the closures that would result in ongoing finishing work would also make great "Metrolinx bungles another project again" articles.
Journalists are vultures and they will spin even the smallest thing into a huge problem. Better to have them write that its delayed and open when its ready and working well.
I've been seeing vehicles regularly between the DVP and Victoria Park since about New Years. Was there a pause? Offhand, I haven't seen much on weekends before.with the resumption of LRT testing along the line does anyone know if thats because the latest software patch has been applied and/or the track has been fully repaired?
Journalists?opportunities for journalists to say its a failure, etc because its slow etc (might not operationally be able to run smoothly with partial open)
I've been seeing vehicles regularly between the DVP and Victoria Park since about New Years. Was there a pause? Offhand, I haven't seen much on weekends before.
"small"I still do not understand why they can't "half open" part of the line, while still fixing those small parts where the problem remains.
On Saturday, May 11 there will be an increase in the number of light rail vehicles (LRVs) travelling along the ECLRT alignment as part of testing work for the project. This work will ensure that all software and control systems are tested and work properly.
A good day for LRV-spotting!