Unless there are some serious issues underground, then 2026 could be an opening day, but 2025 will be the opening day at this time.I'm still firmly in the position that I would be very surprised if it doesn't open in 2024, some time between September and December.
MAYBE something goes wrong and it gets pushed into 2025 - but most certainly not 2026.
With Acciona being selected as a proponent for the Ontario Line, I already see the writing on the wall for that project. It's going to be delayed. The Crosstown West project I see opening close to schedule +/- 6 months.For some reason I have faith in the Ontario line and ECWE being done on time. If you go back far enough, I was optimistic this would be done last year and definitely this year, but right now I don't have a clue as to when the crosstown will actually open
What part is Acciona supposed to do on the Ontario line? What makes them skeptical to you?With Acciona being selected as a proponent for the Ontario Line, I already see the writing on the wall for that project. It's going to be delayed. The Crosstown West project I see opening close to schedule +/- 6 months.
The Crosstown line is the gift that keeps giving; Verster alluded that the earliest this thing would open is late 2024. So realistically speaking, I dont expect it to open until 2025.
What part is Acciona supposed to do on the Ontario line? What makes them skeptical to you?
Just want to take a brief moment to note that we're all going to be potentially severely screwed with Acciona being selected. I knew that name rang a bell, because they've been involved in all of these messes which have had significant issues:
Herb Gray Parkway (Windsor Essex Parkway):
![]()
Ontario government admits mistakes in Herb Gray Parkway construction
Cost overruns and oversight with the Herb Gray Parkway project were discussed in Queen's Park again today as Windsor-Tecumseh MPP Percy Hatfield charged that the government has made major mistakes in its construction.windsor.ctvnews.ca
![]()
Windsor Parkway concessionaire gets fined for delays | Infrastructure Finance & Investment
Jim Lyons, Windsor Construction Association (WCA) executive director, stated:www.infrapppworld.com
Walterdale Bridge:
![]()
Walterdale Bridge still cost Edmonton $155M, even after contractor paid damages for delays - Edmonton | Globalnews.ca
Edmonton taxpayers paid full price for the Walterdale Bridge, despite fines that were levied against the contractor following major delays in the project.globalnews.ca
Site C Dam:
![]()
Site C dam to be delayed a year, more than $5B over budget, B.C. says | Globalnews.ca
The project is now expected to be completed in 2025, a year after its original completion date.globalnews.ca
![]()
Site C dam delayed, costs jump to $16-billion
Premier says its too late to go back despite project challengeswww.theglobeandmail.com
Broadway Skytrain Extension
![]()
Broadway Subway’s revised service date disappears from project reports
Total project completion was last listed as being March 30, 2026www.biv.com
And for fun, things got so bad in Vancouver with the North Shore Wastewater Treatment Plant project that they had to fire Acciona:
Edited to account for Windsor Essex Parkway/Herb Gray Parkway
I predict an O-Train like debacle. So, yes Sept-Dec 2024 is the grand opening. Within a fortnight it's all gone to shite and shutdown again for six months for rectification.I'm still firmly in the position that I would be very surprised if it doesn't open in 2024, some time between September and December.
MAYBE something goes wrong and it gets pushed into 2025 - but most certainly not 2026.
I genuinely believe that Metrolinx watched the Ottawa mess and will not open the line until it is absolutely ready. They have taken enough Ls with the delays already, and I am sure they want the opening to be a win.I predict an O-Train like debacle. So, yes Sept-Dec 2024 is the grand opening. Within a fortnight it's all gone to shite and shutdown again for six months for recitation.
As they observed Ottawa’s experience, Metrolinx likely thought the O-Train was absolutely ready. But in addition to thirteen other faults, they’d not taken into account how the passengers would interact with the doors. There will be something on the Crosstown that Metrolinx has overlooked that causes a shutdown after a brief opening. This organization does not have a record of seeing the whole picture before acting.I genuinely believe that Metrolinx watched the Ottawa mess and will not open the line until it is absolutely ready. They have taken enough Ls with the delays already, and I am sure they want the opening to be a win.
Metrolinx did not have anything to do with the O-Train.Metrolinx thought the O-Train was absolutely ready.
Right. I’ll edit that better. What I meant was…Metrolinx did not have anything to do with the O-Train.
What's the door in interaction issue?




