Photos: The drilling rig arrives and begins boring the holes to plant the i-beams. The yellow crane is used to unload more beams (October 2019).

A4-01-DSC05052.jpg A4-01-DSC05054.jpg A4-01-DSC05055.jpg A4-01-DSC05056.jpg A4-01-DSC05057.jpg
 
Last edited:
From Nov 2019 thru Jan 2020 the boards are wrapped in a protective orange tarp, and the crane is erected. It takes just under 4 mins for the operator to descend at the end of the day.
A7-1-DSC05708.jpgA8-0-DSC09473.jpgA8-1-DSC05749.jpgA8-1-DSC05753.jpg
 
BY June and July 2020 there has been much progress on the walls and the floor of the underground level. Staircase has been installed to allow the crew to get up to ground level.
A8-3-DSC07391.jpg A8-4-DSC07686.jpg A8-5-DSC07689.jpg A8-6-DSC07690.jpg A8-4-DSC07687.jpg A8-7-DSC07963.jpg A8-7-DSC07972.jpg
 
Some of the walls for the first and second level apartments begin to appear in Feb thru April of 2021, and a lot more construction material is on site.
A9-01-DSC01164.jpg
A9-01-DSC01166.jpg
A9-01-DSC01270.jpg
A9-01-DSC01271.jpg
A9-03-DSC09181.jpg
 
Last edited:
Some close-up shots (June 2021) of the crane delivering a bucket of cement to the crew, and they skillfully pour it into the wooden framing to create the walls of each apartment unit. The floor and walls for level 3 is taking shape.
A9-03-DSC09189.jpg
A9-03-DSC09194.jpg
A9-03-DSC09197.jpg
A9-03-DSC09188.jpg
A9-04-DSC09203.jpg
 
Last edited:
The rendering doesn't make it look that bad for an infill suburban condo project. But if you have to say you're the highlight of Mississauga, you probably aren't.
 