Did they ever finish the snails pace Exhibition GO construction that had been going on for the past decade? Funny to think after that we are going to be tearing a lot up there again.
that construction project has been sitting abandoned since 2016. It was procured prior to the GO Expansion program and once GO realized Exhibition Station would need to be substantially revised, they basically just stopped construction and cut their losses. There hasn't been active construction at Exhibition in over 5 years at this point.

A lot of what was done in 2013-2016 is basically just going to get ripped out now. And rightfully so, it was a crappy project.
 

W. K. Lis

Superstar
Member Bio
Joined
Dec 24, 2007
Messages
21,998
Reaction score
12,120
City:
Toronto
A little off topic, but did this need an EA? If not, why can't we just get building additional streetcar trackage elsewhere in the City
We should have built the 512 ST. CLAIR west extension to Jane Street/Scarlett Road by now.

1641843131200.png
 

W. K. Lis

Superstar
Member Bio
Joined
Dec 24, 2007
Messages
21,998
Reaction score
12,120
City:
Toronto
We should have built the 512 ST. CLAIR west extension to Jane Street/Scarlett Road by now.

View attachment 374120
The anti-transit, anti-pedestrian, anti-cyclist lobbyists use the EA (Environmental Assessment) to place roadblocks on projects that may hinder the almighty automobile. Wonder if any of the NIMBYs fighting Ontario Line's routeings, stations, storage facilities, etc. are really anti-transit lobbyists?
 
Last edited:

toronto647

Active Member
Member Bio
Joined
Mar 7, 2020
Messages
493
Reaction score
945
IO P3 Market Update - January 2022

On first glance seems like the project has been delayed. Kind of disappointed the RFQ for the northern civil, stations and tunnel won't come out until July to September 2022. Would have been great to see it before the June elections.

Ontario Line – Rolling Stock, Systems, Operations and Maintenance AND Southern Civil, Stations and Tunnel
  • Contract Execution (between October to December 2022)

Ontario Line – Northern Civil, Stations and Tunnel
  • RFQ July to September 2022
  • RFP Jan to March 2023
  • Contract Execution July to September 2024

 

generalcanada

Active Member
Member Bio
Joined
Feb 20, 2020
Messages
462
Reaction score
780
doubt it.
It depends on if the rolling stock operator wants to show a similar model off.

We dont know if theyre doing a custom unit or one "off the shelf"
 

CharmAlarm

Active Member
Member Bio
Joined
Dec 7, 2007
Messages
408
Reaction score
211
Still don't know what the rolling stock will look like. Thought they would have had a winning bid by now.Will a mock-up appear on the grounds of the 2022 Canadian National Exhibition? 🕰️

From link.
View attachment 374756

From link.
View attachment 374757
Slightly more detail here in today's Infrastructure Ontario quarterly report. Contract execution for rolling stock (bottom of pg. 3) will be sometime between Oct-Dec.2022:

 

generalcanada

Active Member
Member Bio
Joined
Feb 20, 2020
Messages
462
Reaction score
780
interesting piece by toronto life.
really goes in depth behind the scenes with the jimmie simpson people, the minto place people. gives perspectives from all sides.
 