Is there work stoppage due to the lockdown?
There has been no lockdown work stoppage . Work stops only on the weekends and holidays - the Portland Commons site normally has a five day week. Work took place as normal every day last week, and is active again this morning.
 
May 6, 2021

DC1FFBE9-2294-43A2-9F5B-753BC7595777_1_201_a.jpeg



8406903B-8707-4D07-8BA0-D956850DFFBE_1_201_a.jpeg
 
Wednesday, may 12.

Perimeter hoarding and sidewalk coverings are now being set up for the Portland Commons project. Three photos, the first one is of the hoarding along Portland Street, the next two are east and west views of the pedestrian walkway enclosure along the north side of Front Street.

20210512_165347.jpg


20210512_165515.jpg


20210512_165621.jpg
 