Valera Construction Update (October 2021) \r\nBuilding A: Concrete pouring has been completed up to the eighth level and level nine will be complete by the end of this week.\r\n\r\nBuilding B: Window installations have been completed up to the third floor and work has begun on the fourth floor amenities, including the outdoor pool.\r\n\r\nTowns: Framing is up to 75% complete for some of the blocks, and other blocks are scheduled to begin framing very soon.