Edward Skira

http://skyrisecities.com
Staff member
Member Bio
Joined
Apr 22, 2007
Messages
16,175
Reaction score
21,199
IMG_7417.JPG
IMG_7423.JPG
IMG_7422.JPG
IMG_7421.JPG
IMG_7420.JPG
IMG_7419.JPG
IMG_7418.JPG
systhumb_428-ext-cam-017-03.jpg
 
Valera Construction Update (October 2021) \r\nBuilding A: Concrete pouring has been completed up to the eighth level and level nine will be complete by the end of this week.\r\n\r\nBuilding B: Window installations have been completed up to the third floor and work has begun on the fourth floor amenities, including the outdoor pool.\r\n\r\nTowns: Framing is up to 75% complete for some of the blocks, and other blocks are scheduled to begin framing very soon.

96CD4616-10A9-4DB9-9326-448A01BEB816.jpeg


F6804E34-0640-416B-9100-F46FA47C20E7.jpeg


E6B2D542-A80C-4CE2-BFAF-CE922EF829E5.jpeg


 
2/2 ;
Tower A 🏢
- Drywall nearing completion for Level 2 units
- HVAC, electrical, and plumbing rough-in complete through Level 3
- Suite framing complete through Level 5

Tower B 🏢
- Windows being installed on Level 2 & 3
- Concrete work is mostly complete. Level 9 slab is fully poured and verticals are almost complete up to Level 10.

Townhomes 🏠
- Stucco installed in Blocks 3 & 7
- Framing across the townhomes is either in progress or complete
- HVAC, electrical, and plumbing rough-in started in many homes already
- Drywalling should begin soon
 
  • Like
Reactions: AHK
Valera Construction Update – February 2022

There are lots of exciting things happening at Valera! Since our last construction update, a lot has been done at Valera.

Building A 🏢
- Framing is complete on Level 7 and started on Level 8
- Drywall is complete up to Level 5
- Kitchen and flooring installation has begun on Level 2

Building B 🏢
- Windows are fully installed on Level 4 and started on Level 5
- Hallway framing to begin shortly

Townhomes 🏠
- Roof framed in Block 1, drywall and stucco underway in Block 2
- Drywall and taping ongoing in Block 3, plumbing rough-in started in Block 4

- All units being framed in Block 5, foundation walls being constructed in Block 6
- HVAC and electrical underway and stipple, trim, and railings install getting started in Block 7

As the weather thaws and spring rolls in, we are eager to keep the progress moving toward getting all units drywalled and finishes started.
6833DC37-B81F-4ACC-BB6A-C5EE488F0BD2.jpeg
179C67BD-7569-466D-A78B-AFF8A935A9B3.jpeg
CDE29D9E-F55F-4499-A02E-DA8FF20FD6EB.jpeg
7E4FF193-5CC8-4A5B-830F-FE963E9E1857.jpeg
7407E445-D9CE-4809-9FB8-A24530C14599.jpeg
84174C44-5F20-4FC7-A82E-79AEB47462E7.jpeg
 
While I was going to shop at Fortinos but we don’t have pictures and we have some update: The second crane at ADI Valera Condos has come down, still under construction, more windows still installing and townhouses looking well.
 

Back
Top