The new rendering updated in the database. No new information updated. Rendering taken form the architectural plan via Site Plan approval.

PLN - Architectural Plans - DEC 8  2022-189.jpg


PLN - Architectural Plans - DEC 8  2022-190.jpg
 

AlbertC

Superstar
Member Bio
Joined
Apr 25, 2007
Messages
20,536
Reaction score
53,288
City:
Toronto

Work on a geothermal heating and cooling system is to begin soon, and occupancy is scheduled for July 2025.
 

Jimto

New Member
Member Bio
Joined
Sep 22, 2020
Messages
85
Reaction score
65
Pile driver still on site but no "action" yet.
UPDATE: there is some activity there but it doesnt appear to be full on yet.
 
Last edited:

mjl08

Senior Member
Member Bio
Joined
Apr 13, 2008
Messages
4,079
Reaction score
2,622
Overall, I'm looking forward to this project. It could probably be a few stories taller, but the colour and street-level retail presence looks promising.
 

Jimto

New Member
Member Bio
Joined
Sep 22, 2020
Messages
85
Reaction score
65
As the work progresses, the incursion on the public space increases. Fences are now being replaced by concrete barriers, pushing further out onto sidewalk and no effort is being made to clean mud from sidewalks.

There was a virtual community meeting to review the site plan and construction management plan last night. Did anybody attend?
 

Northern Light

Superstar
Member Bio
Joined
May 20, 2007
Messages
25,600
Reaction score
68,878
As the work progresses, the incursion on the public space increases. Fences are now being replaced by concrete barriers, pushing further out onto sidewalk and no effort is being made to clean mud from sidewalks.

There was a virtual community meeting to review the site plan and construction management plan last night. Did anybody attend?

The construction staging report for this one is headed to the next meeting of TEYCC:

 