Steel framing is all up at Science Centre station:
That's true to some degree. Those who were pushing for Transit City never thought about a DRL.DRL was never thought to have gone up to here to the science centre and besides the currently alignment along leslie will have little bearing on the interchange station.
What about the celestica ramp on the southside? you will have to redevelop the entire intersection there if you put the row on top of it.
Flyover video
Flyover video
LOL @ 1:25 in that video. Illustrates how badly staging of construction has been on this project. Literally two rows of left turning cars turning into each other.
It was always designed to be put in the middle of the road at that location. Rob Ford got ML to change to an elevated line with ML doing little work on it. The plan was reverted to the original EA so there will be no need to consult with city council for an EA amendment. ML thought one amendment by shifting the line at Black Creek to an elevated structure was enough trouble. No one wanted to redo the EA and reconsult with the community again. They were getting close to tendering and more changes risk more delays.It was put in the centre of the road by planners and designers that had no plans or even remote thoughts of a DRL subway being built.
When this line was proposed to be fully grade-separated in 2011 - it would have worked perfectly with a DRL.
Those that worked to cancel the Eglinton-Scarborough Crosstown and put this line in the middle of the road, especially through Leslie, are the same ones who never want a DRL built.
Since they were able to shift the tracks north over Black Creek, they could have done the same too for Leslie. ML was keen to have the line connect to the MSF without traffic so they can use ATO. If they haven't done so, I bet half this thread will be full of people whining about it.The alignment will be affected all the way to the Brentcliffe portal if you want to maintain the straight. I'm not sure if its worth realigning the entire stretch of eglinton from laird to don mills just for leslie. Also
structurally it will also be affected to build a tunnel right next to a shored up section of land. Im sure many traffic engineers were consulted on this and this is the best result overall. Besides, they can get signal priority to easily address your concerns of leslie.
Clearly no one can follow line markings in TO. The lead car has to take most of the blame, the rest of the idiots followed. "I'm gonna turn like I do in every intersection without looking at what i'm driving into". I don't know what lane the east to north lead car is turning into? Maybe he hopes to hit the right turning bus? Or the pedestrians behind the pylon?
It was always designed to be put in the middle of the road at that location. Rob Ford got ML to change to an elevated line with ML doing little work on it. The plan was reverted to the original EA so there will be no need to consult with city council for an EA amendment. ML thought one amendment by shifting the line at Black Creek to an elevated structure was enough trouble. No one wanted to redo the EA and reconsult with the community again. They were getting close to tendering and more changes risk more delays.
That is very weird.LOL @ 1:25 in that video. Illustrates how badly staging of construction has been on this project. Literally two rows of left turning cars turning into each other.
Just to be clear, is my memory not correct that while Mayor Ford may have encouraged ML to look at an elevated route for the Laird-Kennedy portion, he didn't get it passed through Council. When the matter finally did come to Council they voted for the EA recommended surface alignment (there many have been other LRT lines included as well in the motion).
In other words, there was no public information provided (by City staff or ML) on what an elevated option would have looked like or involved. Also, for "The plan was reverted to the original EA so there will be no need to consult with city council for an EA amendment" do you mean "The plan was reverted to the original EA so there waswill beno need to consult with city council for an EA amendment"?
I've not even solid indication of that. He campaigned on no line of any kind on Eglinton.I thought Rob Ford wanted the entire line underground ...
Neighbours pushing for elevated with all the extra noise? That would be unique. Car drivers who didn't live nearby maybe.I think locals were in favour of the elevated alignment.
I think locals were in favour of the elevated alignment.Since they were able to shift the tracks north over Black Creek, they could have done the same too for Leslie. ML was keen to have the line connect to the MSF without traffic so they can use ATO. If they haven't done so, I bet half this thread will be full of people whining about it.
The Memorandum of Understanding said the line would be underground, with portions in Don Valley and near Eglinton elevated. With the two branches of the Don River, that means over half elevated.I thought Rob Ford wanted the entire line underground, so I'm unsure where @Steve X gets that "Rob Ford got ML to change to an elevated line" (unless it's non-public information).
They did not consider any options. They said due to slope stability problems, it was imposible to put the Brentcliffe portal in the original EA approved location, so they proposed tunneling all the way to Don Mills. When locals complained about losing the Leslie stop, they said that station (underground, but deep) would cost $60M and that was too much. I don't recall any complaints about losing the Ferrand stop - which was the correct reaction. Then when the public was still unhappy, they reverted to the "impossible" original EA Brentcliffe portal and routing through Leslie.That aside... not mentioned at all in this discussion is that Metrolinx pushed to have the section between Laird and Don Mills changed to a bored tunnel beneath the Don Valley, with the Leslie and Ferrand Dr stops eliminated. They may have considered other surface options, but those were rejected in favor of a tunnel. Of course the documents have since been deleted as per Metrolinx's usual contempt for transparency, however I managed to pull a few slides from the deep web from a public consultation.
I had read Steve for a number of years prior to this date. He always was convinced that putting the LRT in the median through Leslie was an oversight and it was bound to be corrected in detailed design. We kept waiting and waiting, but it never happened. I am convinced that some in the design team preferred it in median as it would hurt cars significantly.This article goes into much more detail as to what transpired at the time, including what happened with the "south side alignment".
![]()
Metrolinx Announces Design Changes and Public Meetings on Eglinton LRT (Update 8)
Updated June 17, 2013 at 6:15 pm: In the comment thread for this article, there has been substantial discussion about a “south side option” for the Eglinton LRT between the portal at Br…stevemunro.ca
I recall this. Basically they said they screwed up the design and there was no time to fix it.As for why we switched back to the original plan, you and @Steve X are correct. To elaborate... political posturing by councillor Robinson on behalf of some Leaside residents put pressure on Metrolinx to back down on eliminating the Leslie stop. The only way this would be feasible is to either go back to the original surface alignment, or pursue the "south side alignment". However because the latter would have required approval from city council, which at the time was too busy ripping up transit plans every six months and dealing with the mayor's crack scandal, Metrolinx had no confidence in their ability to make a decision in a timely manner and stick with it. Needless to say, "Fuck it, we're not touching you guys with a ten foot pole" was the easiest thing to do.