One year ago I mentioned that this is the same developer as 'Post Loft Condos' on Queen St E. That development after more than 5 year is a weed strewn lot in prime Leslieville. This obviously says something about something!
Yes it does. Did you get you money back in that project? He also has another called THEO which the sales office and sign are now fully covered in graffiti
 
Yes it does. Did you get you money back in that project? He also has another called THEO which the sales office and sign are now fully covered in graffiti
I did not invest in any of 'Condoman's" projects. I live very close to the failed 'Post loft Condos' in Leslieville.
 
Last edited:
view-02.jpg


view-03.jpg
 
The mortgagee (Cannect) had advanced a minor variance which was approved by CoA and is now being affirmed in the site plan agreement. The primary changes are an increase in total residential units from 30 to 90 and a decrease in total vehicular parking from 41 to 29.

Updated design by RAW Design:
p1_1.jpg

p1_2.jpg

PLN - Architectural Plans (2 of 2) - Architectural Plans_507-511 Kingston_October 24 2024_Part...jpg

2.jpg
 

Attachments

  • p5_6.jpg
    p5_6.jpg
    109.6 KB · Views: 97
  • p5_7.jpg
    p5_7.jpg
    184 KB · Views: 118
This site is now tagged for 30-Units of “Affordable Rental” for 50 years in PHC item -

PH23.5 - From Concept to Construction: Creating More Homes Across the Housing Continuum​


IMG_4348.jpeg


Deal is with - “A community-driven, Indigenous-led nonprofit dedicated to providing affordable housing solutions for Native Canadians.”

 


Concerns over condition of construction site on south side of Kingston Road raised by residents


East Toronto residents are continuing to voice their concerns with the lack of maintenance at a prominent construction site on Kingston Road.

The site at 507-511 Kingston Rd., has been vacant for more than a year and a half. In the past, concerns about the site on the south side of Kingston Road between Lee Avenue and Waverley Road have centred around the large drop down into the slope beyond.

However, a recent email to Beach Metro Community News also cited garbage, bags of dog poop in a tree, and damaged sidewalk in front of the construction fencing as neighbourhood concerns. The email was titled “Dog poo adorns the pit at 507-511 Kingston Road”.

The site is basically now a fenced-off pit spanning 9.5 metres in height (just over 31 feet) from the end of Wheeler Avenue at the south end up to Kingston Road at the north end.

Property owner Marcus Tzaferis said he has been made aware of the site’s current state by Beaches-East York Councillor Brad Bradford’s office, and that work is being carried out to clean it up.

“We were unaware of the garbage accumulation at the site and sincerely apologize to the neighbourhood for any inconvenience this has caused,” said Tzaferis in an email to Beach Metro Community News.

“Our team was on-site yesterday to address the issue, and we will continue to monitor the location closely to ensure any future dumping is handled in a timely manner.”

In a recent statement to Beach Metro Community News, Bradford said the responsibility to make sure the site is properly maintained is on the property owner.

“It’s up to each property owner to make sure their property is clean and well-maintained – whether the site is vacant, under construction, or occupied,” said Bradford. “When properties are not maintained, city bylaw officers can inspect and issue a notice requiring the owner to clean up the site.”

The first zoning bylaw application to redevelop the 507-511 Kingston Rd. site was submitted more than nine years ago, in December of 2016.

By early to mid 2024, the existing buildings on the site were torn down and the slope was dug out. Work then halted on The Condoman Development’s The View project on the site, and residents have been left unfavourable views of an empty pit with metal framing and sand.

The latest proposal for the site was for an eight-storey residential building that was approved in July of 2024.

Bradford said a plan bringing supportive housing and affordable rental units to the area is now nearing final approval.

“507 Kingston is an exciting project. It will be home to a fully affordable rental building, including 30 units of supportive housing,” said Bradford.

“I have helped secure funding and support from the city for this project, and it is awaiting final approval from CMHC (Canada Mortgage and Housing Corporation) before they can get shovels in the ground.”

In the housing market, “awaiting approval” from CMHC often means a developer is securing financing or insurance to ensure a project’s viability.

Tzaferis said he is currently working with the municipal and federal government to ensure construction of the affordable and supportive housing on the site can begin.

“We are working closely with the councillor’s office, the City of Toronto, and the federal government to bring forward a sustainable and affordable housing project that is much needed in the community,” said Tzaferis.

Despite the hardships afflicting the real estate market, Bradford said he’s “optimistic that we will see construction resume soon, creating more homes for people in our community who need them.”
 


Concerns over condition of construction site on south side of Kingston Road raised by residents


“507 Kingston is an exciting project. It will be home to a fully affordable rental building, including 30 units of supportive housing,” said Bradford.

“I have helped secure funding and support from the city for this project, and it is awaiting final approval from CMHC (Canada Mortgage and Housing Corporation) before they can get shovels in the ground.”

In the housing market, “awaiting approval” from CMHC often means a developer is securing financing or insurance to ensure a project’s viability.

Tzaferis said he is currently working with the municipal and federal government to ensure construction of the affordable and supportive housing on the site can begin.

“We are working closely with the councillor’s office, the City of Toronto, and the federal government to bring forward a sustainable and affordable housing project that is much needed in the community,” said Tzaferis.

Despite the hardships afflicting the real estate market, Bradford said he’s “optimistic that we will see construction resume soon, creating more homes for people in our community who need them.”

@HousingNowTO is flagged to comment on the excerpt above.
 