And in typical ML fashion, the notice I posted is no longer listed on the notices page, but still accessible by link.
You're absolutely correct. They're doing work in the middle of the intersection for the guideway / rails from April 17th 2026 to May 25th 2026.
The work on Rathburn may not happen as per the notice date, but will happen in May as there is very little guideway to be dug up other than intersections.
April 26,
Do to an unplanned event, had to rent a car that allow me to try to do a video of the corridor today that turnout to be a good and bad thing. A lot of work taking place on a Sunday that will become more a norm than the current 6 day week. Even hydro was doing work south of Dundas.
This Sunday will mark a first for the protestors at Burnhamthorpe Intersection as it was a gridlock going north that I used Robert Speck around Burnhamorpe and Absolute area with a fair number of police officers dealing with traffic. The protestors will not be allow in the area do do their setup.
I counted 10 LRV's in the yard and could be a few more as they are on a different tracks than the ones shot from a plane a few weeks ago.
All the guideways that were dug up all have concrete curbs including the areas for left turns, Ray Lawson intersection has the guideway on both sides of it now dug up to the crosswalk but not to the full depth.
Missing curb for the 407 bridge is a high one that is formed like the ones on the bridge.
Guideway on the south of the 407 bridge area ready for concrete work.
Crews were preparing the driveway for a business by the 407 terminal foe paving with all concrete work done.
Crews working on the tracks for the Eglinton Station so it can be pour this week.
Work taking place on the wye area.
Crews working on formwork to allow the topcoat for the whole block for Burnhamorpe station
There are now 10 OS poles from Matthews Gate to Fairview.
Crew working on John St Intersection
Hard to say if that last section of concrete south of Floradale was pour but Paisley base is poured.
Haff of the track work from the fire station toward Paisley has been poured with the rest of the driveway waiting the topcoat to be pour this week.
Small amount of track work still needs to be place from the Queensway to Sherobee intersection to be place on Monday to allow the area to be ready for concrete to be pour for it.
Rails been place in the guideway south of Sherobee.
Crews working on the QEW guideway and need a closer look at the east pier for the QEW as it all chip away or have added rebar for more protection from the LRV's
All guideway from Pinetree to Pinewood dug up except that one driveway for those townhouses. All guideway poured from Pinewood to Mineola waiting track work
Forming in place for Mineola Station and hard to say if it has seen concrete poured for it..
Otherwise, noting new for the rest of the corridor not noted.