The "missions" chart is informative - the interesting thing to watch is whether that chart may change with time. Hopefully, it stays constant without erosion or rethinking of the end state - and the progress towards the stated end state reflects commitment to the stated work items. That kind of discipline over scope would be a big step forward for ML.
A few details that I noted
- Some Baseline budgets have been increased, none have been cut
- The Barrie line suggests second track Strachan to Rogers, at Caledonia Station, at Downsview Park Station, but does not indicate continuous double tracking all the way from Rogers to Snider South - despite a lot of work completed to prepare the subgrade for double tracking
- Kitchener line continues to refer to grade separation at Silver Jct, versus east of Georgetown
- Second platforms at Guelph, Agincourt and Milliken are shown as complete - technically true but without usable track, a bit of a stretch
- Construction said to be underway to add second track Highland to Underwood - as we know, there is only one major construction item needed to accomplish that ie the missing bridge. Is it really under construction?
- A Spadina-Front station is now on the map
Pinning ML down on tcd's is never easy but it would be helpful to at least highlight items that are likely to be completed this year. Without creating unrealistic predictions, the reality of the timeline to those more distant items ought to be clearer.
- Paul