M Marcus CLS Active Member Member Bio Joined Jan 8, 2024 Messages 182 Reaction score 311 Jan 9, 2026 #16 Additional shots in the hole. Noted that the base of the angled steel beams along the northerly wall were previously exposed are now backfilled.
Additional shots in the hole. Noted that the base of the angled steel beams along the northerly wall were previously exposed are now backfilled.
M MasterApex New Member Member Bio Joined Sep 29, 2025 Messages 4 Reaction score 1 Mar 11, 2026 #17 Are there any updated on this project? How did they get around the utility pipes? Has structural construction actually begun? Any new pictures?
Are there any updated on this project? How did they get around the utility pipes? Has structural construction actually begun? Any new pictures?
M Marcus CLS Active Member Member Bio Joined Jan 8, 2024 Messages 182 Reaction score 311 Mar 13, 2026 #18 Based on construction progress so far I am doubting if a utility pipe was ever encroaching.in the hole. This project is now called Aurora Apartments as seen on the banner..
Based on construction progress so far I am doubting if a utility pipe was ever encroaching.in the hole. This project is now called Aurora Apartments as seen on the banner..