  1. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    Here is a new picture from my window......its looking good!
  2. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    The are working on lvl 2 floors and they are also working on parts of floor one still, the underground has finally been completed and they have power to the garage as the lights are always on at night. I think by the end of this week and if it does not rain they should be pouring the east part...
  3. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    Well the area has been changing and the the gun play was at Dupont Satation and that is two subway stops going East towards Bloor. The recent police shooting on Campbell is still an unknown and there were conflicting stories in the media. But I can tell you that the area has been changing since...
  4. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    At what per square foot did you buy at? In 2008 I bought at 318.39 @ 735 sqft. for a 14th level unit and thats in P1.
  5. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    Well lets just hope that our dates for moving will be on time..... Has anyone been told the increased value on their unit yet?
  6. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    I did have a look today at the site and I got to talk with one of the guys doing the forms and of course he is one of the workers and not the contractor, but he did say he thinks that July will be the month that all the structure will be completed. Its really hard to put the site in...
  7. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    Well they have now been building above grade this week.......that is a huge milestone...the ramp to the underground parking was also completed.
  8. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    You can't see it but they have started to excavate P2 and the entire P1 sub floor has now been completed
  9. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    Well as many of you know they are working pouring the footings and columns, they have poured the first floor pad and also they do now have electricity running in the lower part or the parking garage. The workers have been going at a very steady pace and every day they are pouring and...
  10. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    Hey, As you can see from teh picture they have been doing footings and the colums. As of this week they are starting to get the 1st floor scafolding and forms constructed, but they still are working at the sub floor and constructing colums from west to east and the outside walls are also...
  11. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    Yes...4sure, once they get the footings complete which they have completed about 80% now they can pour all winter they might be ready for next Sept 2012.....and I mean MIGHT lol.....lets keep our fingers crossed. They have been going at a steady pace and they are on site at 6:30 everyday and...
  12. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    I assume that any units left will be sold by the agents for Fuse who are the same that sold Upsidedown.
  13. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    Well I was right....they have started the base for the craine....I stopped to have a look today....and did see the rebar and base of the craine all wired up...and ready to poure the concrete.....so I am sure we will see the craine this week or next week on site. Rikk
  14. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    Hi Rob, Good pics.... I think they have also dug a large padding for a craine....in the second picture you can see that they pourde concrete in the bottom and the area they dug out is about 20 x 20 feet square. Its just a guess....I was looking at the site yesterday......also the...
  15. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    Site update: Some rebar has been deliverd to the site this week and there are iron workers too, the excavation site has gotten deeper and again land suverys have been done. Looks like the site is gearing up for major work. Rikk
  16. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    They are still excavating................ :eek:
  17. R

    Upside Down + Fuse Condos (Channington/Brownstone, 14s x2, 26s x2, Burka)

    I just got home now and had a very fast look.....they are tying in the sewage pipe for the underground into the existing one, also the excavator on site is now digging deeper and I thought they would be done but now I am wounder how far are they going... also to note TMG has now posted the...