News   GLOBAL  |  Apr 02, 2020
 9K     0 
News   GLOBAL  |  Apr 01, 2020
 40K     0 
News   GLOBAL  |  Apr 01, 2020
 5.2K     0 

  1. A

    Toronto Toronto | Forma | 308m | 84s | Great Gulf | Gehry Partners

    July 2 - A rebar steelworker's nirvana:
  2. A

    Toronto Toronto | Theatre District Residence & Riu Plaza Hotel | 156.05m | 49s | Plaza | BDP Quadrangle

    July 2: Occupancy of the north tower has started, been underway for a couple of weeks (south tower occupancy started a while ago). The Widmar sidewalk itself looks to be ready, however work on the townhouse frontage is continuing. Still some missing cladding at the top of the north tower.
  3. A

    Toronto Toronto | Central Condos | 138.98m | 46s | Concord Adex | DIALOG

    July 2 - Almost, but still not quite all finished on the exterior. Getting this last little bit across the finish line has been taking forever.
  4. A

    Toronto Toronto | QRC West Phase 2 (Queen Richmond Centre West) | 35.96m | 7s | Allied | Sweeny &Co

    July 2 - Finally, after several months of what appeared to be no activity on the QRC West Phase 2 project, signs of life from the tenant fit-up contractor on the site: Queen Street Doorway: Portland Street Entrance: Construction equipment inside on the ground floor:
  5. A

    Toronto Toronto | 369 Queen Street West | ?m | 3s

    July 2 - Progress at 369 Queen Street West seems to be quite slow, and no one appeared to be on site today.
  6. A

    Toronto Toronto | Ontario Line: Queen-Spadina Station | ?m | 1s | Metrolinx | HDR

    July 2. Some interesting work going on at the south-west corner. Sections of concrete pump distribution piping were being lifted out of one of the shoring holes. Apparently, concrete is not poured into the hole from the top, but actually pumped down the piping directly to the bottom of the...
  7. A

    Toronto Toronto | 123 Portland | 49.3m | 14s | Minto Group | Sweeny &Co

    July 2 - Building exterior looks complete. The second photo shows a very last touch underway - the protective covers of the Toronto Hydro lines are being removed along the Adelaide Street frontage of the building. Hopefully the final lane closure barriers can then be removed.
  8. A

    Toronto Toronto | 543 Richmond Street West | 47.24m | 15s | Pemberton | BDP Quadrangle

    July 2 - Occupancy proceeding while finishing touches to the exterior are underway. For a building of its size and prominence, the main entrance still feels on the underwhelming side. Juliette windows: Richmond Street sidewalk - complete with trees planted. Portland Street sidewalk...
  9. A

    Toronto Toronto | Ontario Line: King-Bathurst Station | ?m | ?s | Metrolinx | HDR

    July 2: South side of King Street. Rebar nests for caissons being delivered- according to an OTG staffer, 24 metres long North side of King Street: King Street frontage: North property line:
  10. A

    Toronto Toronto | 88 Bathurst | 68.3m | 17s | Hines | 3XN

    July 2: Mechanical components in the mechanical penthouse and on rooftop: South end of 88 Bathurst rooftop: Cladding work on the residential penthouse floor.
  11. A

    Toronto Toronto | Ontario Line: King-Bathurst Station | ?m | ?s | Metrolinx | HDR

    June 27 - mid afternoon: A rebar nest column being lifted and inserted into one of the pile holes on the south side of King Street. It's long.... On its way down:
  12. A

    Toronto Toronto | 88 Bathurst | 68.3m | 17s | Hines | 3XN

    For all intents and purposes - yes. Just some final clean-up going on this morning.
  13. A

    Toronto Toronto | 88 Bathurst | 68.3m | 17s | Hines | 3XN

    Tuesday, June 25:
  14. A

    Ontario Science Centre

    To clarify - from my perspective at least - venality wrapped in communications and messaging just obvious easy pr blunders that make no sense.
  15. A

    Toronto Toronto | KING Toronto | 57.6m | 16s | Westbank | Bjarke Ingels Group

    June 24 - A couple photos of King Toronto in the late afternoon sunshine.
  16. A

    Toronto Toronto | The Well | 174.03m | 46s | RioCan | Hariri Pontarini

    June 24 - The remaining section of external cladding still to be completed, on the west facade of the Tridel Signature Series condominium building, is now underway.
  17. A

    Toronto Toronto | Portland Commons | 71.7m | 15s | Carttera | Sweeny &Co

    June 24: Construction activities along the Front and Portland street levels of Portland Commons are continuing. Also visible in the photos below are a number of shipping frames with building facade components - hopefully this is the shipment of the outstanding items from the original supplier...