    New Ottawa Civic Hospital | The Ottawa Hospital | HDR

    Hoisting preformed decking July 25th.
  2. M

    Andaz Ottawa Byward Market | 56.08m/59.37 | 16s/18s | Claridge Homes | NEUF

    Excavation well underway. Taken July 26th.
  3. M

    Claridge Hintonburg | 99m | 30s | Claridge | architectsAlliance

    Taken yesterday from the Staircase down to trillium MUP.
  4. M

    Roads: Highways in the National Capital Region

    2 shots taken prior to the start of Preston Street HWY 417 rapid Bridge replacement.
  5. M

    327 Richmond Rd | 30m | 9s | CLV+InterRent | Hobin

    2 down 3 to go.
  6. M

    1047 Richmond Rd | 24/127/133m | 6/38/40s | Fengate | IBI Group

    Driving by today noticed 3 pieces of equipment on site. One shovel, one explosives drill rig with large generator. I have no idea about site plan control for this one. After the OLT agreement was reached Re: zoning this project disappeared from Devapps. Is this equipment for 1047 Richmond or is...
  7. M

    1640-1660 Carling Ave. [Former Canadian Tire] | 63/69/78/93/125/135m | 18/20/24/28/37/40s | Riocan | Hobin

    I have taken a couple of walks around the site since the redevelopment of the Recreation club started. I was hoping the two southern wings beyond the covered parking might be demolished to allow for partial developement. It looks like the entire existing building foot print will be used for the...
  8. M

    Aylmer/ Champlain Village/Mixed Use Residential/Brigil

    Correction: Phase 2 will consist of 329 units including a community building with pool.
  9. M

    The Talisman | 72m | 22s | Holloway Lodging | Geiger Huot

    Took photos yesterday while out cycling.
  10. M

    O-Train East-West Line 1 & Line 3

    They have started laying rail east of Island Park Drive towards Tunnys Pasture Stn. Still lots of patch areas to infill where rebar and concrete footings are not yet poured.
  11. M

    Gatineau | Le W/E 2/3 | ?m | 13/26s | Heafey | PMA

    Took a photo from Chaudier Dam. It looks like Tower Crane maybe up for tower 2.
  12. M

    New Ottawa Civic Hospital | The Ottawa Hospital | HDR

    Eastern garage being back filled and tamped down.
  13. M

    Aylmer/ Champlain Village/Mixed Use Residential/Brigil

    Drilling rig and cassons on ground shown further west. That location maybe 9 or 10 story apartment building guessing from renders on the project website.
  14. M

    Aylmer/ Champlain Village/Mixed Use Residential/Brigil

    Phase 2 has commenced construction. According to the brigil website this phase is to have up to 500 units. Photo taken today shows basement level being completed for what I beleive will be another 4 story apartment just west of phase 1.
  15. M

    Aylmer/ Champlain Village/Mixed Use Residential/Brigil

    Champlain Village is mixed use multi residential subdivision planned to have a mix of low to high rise buildings. Phase 1 completed in 2023 consists of two 4 story rental buildings.
  16. M

    O-Train East-West Line 1 & Line 3

    Kitchissippi Station taken April 20, 2024.
  17. M

    Ottawa | LeBreton Arena | Populous

    I found a website Construct Connect which has a database of construction projects for bidding. I presume the subscription is paid as it provides detailed information for a project. Using the public search filter set to Eastern Ontario I found the following. Location: Ottawa- Carleton Region...
  18. M

    O-Train East-West Line 1 & Line 3

    Photos taken April 17, 2024 West end of New Orchard Station
  19. M

    Ottawa | Centrepointe Collective | 65+72m | 21+23s | Richcraft | RLA

    Gave up on the Rideau Canal so went skating at Centerpoint rink. Took a few shots after I was done.