    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    Ww had our PDI, and honestly a little bit disappointed. No sidewalks or clear entrance into the building The lobby is not done, there isn’t even a door to the building No flooring in the hallways yet several of our purchased upgrades were just missing (light fixtures, counter tops, etc) No...
  2. C

    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    The email stated that electrical for the building is still not done
  3. C

    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    We went from April 5th to April 24th to May 9th.... At this rate, maybe we can celebrate the new year in the condo 😭
  4. C

    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    On it! Did they give you a date for the pre-delivery inspection yet?
  5. C

    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    They told us they weren't making the deadline on March 13th, but they gave us the new date less than 10 days
  6. C

    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    Ah we are 3 weeks delayed I am guessing you are on the 2nd floor?
  7. C

    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    Do you think they are trying to delay in hopes that we will back out so that they can try to sell our units at a higher price? I saw this on their google reviews
  8. C

    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    Whats wild to me is that the email we got in March said that there will be a delay due to issues with electrical. But whats bizarre to me is that we got an email in August 2022 that said that electrical was complete for the building. Really makes you wonder what type of games they are trying...
  9. C

    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    We just got an email from the builder. Roof slab is estimated to be completed on September 7th 2022 We have received a tentative occupancy date for Mid January for our unit. So, more delays. But not as bad as we were thinking.
  10. C

    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    Does it still look feasible for a December 5th completion date? (The last date we heard from the contact with the representatives)
  11. C

    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    We also bought in February! We were tempted by that “so soon” move in date 😭 We bought on a lower level so we are also hoping for at least interim occupancy for this year. we are quickly out growing our current space hahah And thank you for your info! I may reach out for more info!
  12. C

    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    Ah, I see! Thank you for this! We lived in a Condo downtown with a ceiling like this. And yes, my husband and I bought a unit in this building. It’s both exciting to see it being built, but scary to think about being a home owner haha
  13. C

    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    Forgive my ignorance, but this doesn’t sound good? I can double check the specs, but I do believe they are 9’ ceilings
  14. C

    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    This was on Saturday. We drove by because i was interested to see how much progress they made in roughly a week
  15. C

    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    My husband took videos, but i don’t know if this forum supports videos? I’ll admit, I am not a good photographer ☺️
  16. C

    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    July 26 2022 They are laying bricks on east side, and putting windows on the west; not a lot of work being done on the south side yet
  17. C

    Toronto Toronto | Terrasse Condos at The Hunt Club | 25.91m | 7s | Sunrise Gate | RAW Design

    Workers on site state concrete should be done within a month.