Dec 05
31339126332_339b11a30f_h.jpg


Leading the crane
31114454440_a91053559a_h.jpg


30676772263_7e16d32c8e_h.jpg


Compressors and the come-along (frame with block and tackle for pulling out those hard to pull caisson sleeves)
31485798975_7d8237d4d2_h.jpg



A very noisy crew
30676771163_91975d1b15_h.jpg


31114446170_f5d7db0bb9_h.jpg
 
Dec 16
30983697464_13fc6f4108_h.jpg


Upper Deck
30983705294_81176e6fec_h.jpg


I believe this is part of the load testing setup (done after the caissons are in)
30983702654_4cbd46898f_h.jpg


Drilling away
30983700744_b7d285858e_h.jpg


High pressure job.
30983695574_6fdce16466_h.jpg


The dentist (working on the teeth)
30983690534_688e3b73f9_h.jpg


30983686964_f2e0524f85_h.jpg


Frozen Clay - fun fun
30983689004_a3030d03f2_h.jpg


30983687954_63bf0ce576_h.jpg



Mantiowac -
30983693224_9de191a695_h.jpg
 
Jan 10
from across the river
31968496310_019953ea92_b.jpg


Jan 14
Second crane going up - note the micro piles being installed - an afterthought ?
32195287582_82bc081e3e_b.jpg


31503243374_d225426a50_b.jpg


Split level foundation pad ?
31503229284_ff6dd0557d_b.jpg


It appears that the big - coupled - rebar is being used for the horizontal as well as the vertical - note the staggered endings (earthquake code ?).
32345660985_2a9e526e7c_b.jpg


extending upper upper Wacker
31968502830_ef10f11c8f_b.jpg



The attention to ascetic detail is impressive, use a crane with rounded weights when the backdrop is a curvy building.
32345616735_ff6905fa86_b.jpg
 
Jan 31
32515136941_f0140748b6_b.jpg


32515132141_f75c67dd08_b.jpg


32484430442_2a7c81b9f8_b.jpg


There appears to be quite a big gap in the mat -
32515124121_c039f676a6_b.jpg


Anyone know the use of the thin (rusted) reinforcing wire - I would think the thick bar would be sufficient.
32637587685_4de2c70ecd_b.jpg


And in upper upper Wacker
32637583765_56effb3d34_b.jpg


32637579145_0865d47382_b.jpg
 
Feb 4
- massive mat pour of 4,000 cy of concrete, 400 truckloads.

started at 8am by 5:30pm they were wrapping up.

31913668943_8c40fbf7c2_b.jpg


31913662573_617132c542_b.jpg


32686708046_e467082407_b.jpg


the next in line.
32574128962_dd26ec270a_b.jpg
 
Feb 20
Heading North on LSD the little crane dead center on the road - the site is where LSD turned before the last straitening.
33042685795_bd73e4fa3d_b.jpg



Feb 21
32886746862_50614e7aa5_b.jpg



Solid concrete - ready for a load
32916125841_c88104baed_b.jpg


Teamwork
32660474450_6c23d46b17_b.jpg


Safety first
33000814336_2a32f3ea73_b.jpg


the new E Upper Wacker
32660457020_31059f355e_b.jpg
 
Last edited:
March 01
Stairway to haven
33192466135_5e6311f6c0_h.jpg


Embed plates - how you weld to concrete.
33192468425_8166b161c8_h.jpg


Load bearing shaft
33192462875_8d9bc03b25_h.jpg


33192460075_6ff9411816_h.jpg


Pouring it on (in)
33150452826_712f8a1772_h.jpg


smooth operators
32347206754_869276d5f7_h.jpg
 
Apr 24
33573582964_f3652a1882_b.jpg


Doka Forms
33573574764_7864069443_b.jpg


34030520900_e9f22e45ff_b.jpg


34030519770_d7352352f4_b.jpg


n.b. break off heads on the bolts - just tighten until they pop off (at a pre-determined torque).
34415427575_68a2eaf36e_b.jpg


34030517820_4dff87d372_b.jpg


Tie off pole for safety lines - used while constructing the deck.
34030515980_f9d09e2b51_z.jpg
 