PERMIT_DATE December 22, 2017
PERMIT_NUMBER 265182845-002
JOB_CATEGORY Commercial Demolition
ADDRESS 10199 - 101 STREET NW
NEIGHBOURHOOD DOWNTOWN
JOB_DESCRIPTION To demolish an existing six storey office building (Bank of Montreal).
BUILDING_TYPE Office Buildings (520)
WORK_TYPE (99) Demolition
FLOOR_AREA
CONSTRUCTION_VALUE 1,000,000
ZONING CCA

PERMIT_DATE December 22, 2017
PERMIT_NUMBER 265182845-003
JOB_CATEGORY Commercial Final
ADDRESS 10199 - 101 STREET NW
NEIGHBOURHOOD DOWNTOWN
JOB_DESCRIPTION To construct TEMPORARY HOARDINGS and occupy sidewalk/boulevard for the demolition of existing office building - Permit expires March 01/18 (former Bank of Montreal) WORK STARTED WITHOUT PERMITS.
BUILDING_TYPE Temporary Structures (999)
WORK_TYPE (99) Demolition
FLOOR_AREA
CONSTRUCTION_VALUE 100,000
ZONING CCA
 

Attachments

  • 20171227_121735.jpg
    20171227_121735.jpg
    203.7 KB · Views: 1,235
BMO demolition could pave way for Edmonton's tallest tower

bank-of-montreal.jpg

Demolition of the former Bank of Montreal building at 102nd Avenue and 101st Street started in early January and is expected to be complete by April. (Art Raham/CBC)

A stone frame and hollow belly are what is left of the former Bank of Montreal building in downtown Edmonton.

Regency Developments began tearing down the structure at 102nd Avenue and 101st Street earlier this week. The company bought the six-storey building last March.

...

Plans for the site are far from finalized but Regency has a vision of what will replace the old building.

The company is planning a mixed-use tower with commercial space on the main level, and a hotel and residential condominiums on top.

"Everybody knows it's one of the premier corners in the core of our city," Dhunna said. "So to bring density and height and shaping that corner, a lot of people are really excited."

...

If approved, the new tower would be 45 to 50 storeys high, making it the tallest condo building in Edmonton.

...

Regency aims to complete the demolition by April and then build an underground parkade.

While this work is going on, Dhunna said the company will look at designs and reach out to potential commercial tenants.

The company aims to start building the tower in mid- to late 2019.

http://www.cbc.ca/news/canada/edmonton/bank-of-montreal-edmonton-regency-1.4485756
 
Last edited:
P1151134.jpg
P1151136.jpg
P1151135.jpg
P1151133.jpg
P1151137.jpg
P1151138.jpg
P1151139.jpg
 

Attachments

  • P1151134.jpg
    P1151134.jpg
    206.3 KB · Views: 1,021
  • P1151136.jpg
    P1151136.jpg
    224.2 KB · Views: 1,042
  • P1151135.jpg
    P1151135.jpg
    173.1 KB · Views: 1,038
  • P1151133.jpg
    P1151133.jpg
    298.5 KB · Views: 1,087
  • P1151137.jpg
    P1151137.jpg
    188.9 KB · Views: 1,035
  • P1151138.jpg
    P1151138.jpg
    259.7 KB · Views: 1,045
  • P1151139.jpg
    P1151139.jpg
    266.8 KB · Views: 1,138

Back
Top