News   GLOBAL  |  Apr 02, 2020
 10K     0 
News   GLOBAL  |  Apr 01, 2020
 42K     0 
News   GLOBAL  |  Apr 01, 2020
 6.2K     0 

unimaginative2

Senior Member
Member Bio
Joined
Apr 23, 2007
Messages
4,554
Reaction score
13
GO Transit must reduce delays, collect unpaid fares

JEFF GRAY

The Globe and Mail

December 12, 2007

Delay-prone GO Transit not only needs to do more to keep its trains on time, it should crack down on passengers who fail to pay their fares, a report by Ontario's Auditor-General says.

Commuters know all about GO Transit's frequent cancellations and delays - wintry weather tends to make it worse - and even Auditor-General Jim McCarter said he was left stranded on a platform this week.

"I take the GO train infrequently, and you know, myself and several hundred people stood on the platform for 40 minutes waiting for the GO train," Mr. McCarter told reporters yesterday. "It is an issue. They've got some serious challenges that really need to be addressed."

Riders on the rapidly growing commuter-rail service endured more than 160 train cancellations and 3,400 delays between October, 2006, and February, 2007, the report says. Over all, only 85 per cent of trains ran on time, nearly 10 per cent off GO's performance in past years.

The audit chastises GO Transit for failing to plan properly for future growth on its rail corridors, resulting in overcrowding. The report also partly blames the delays on GO's complex relationship with the private freight railways - Canadian National and Canadian Pacific - that own 70 per cent of its tracks and actually operate its trains, a problem GO has raised before.

It also criticizes GO for the management of some of its contracts with private consultants and other firms. One, for experts to oversee massive repairs to parts of Union Station, was initially approved as a $275,000, year-long contract but was extended nine times, the auditor said, growing to $25-million, even though GO knew it would need a multiyear contract.

GO Transit's managing director, Gary McNeil, said that kind of contract - which GO's board approved - was pretty standard in the infrastructure business, because bringing in new consultants each year is not practical. Plus, he said, the agency relies on the federal, provincial and municipal governments for its funds, meaning it must take a year-by-year approach.

That lack of long-term funding, he said, is also the reason it might appear that GO Transit operates without sufficient planning: "We'd love to plan without regard to budgets, but we can't."

To partly address the difficult issue of its relationship with the private-sector railways, GO Transit next year is ending its practice of using CN crews and has awarded a contract to operate the majority of its trains to Bombardier.

The move, Mr. McNeil said, will improve customer service by including financial penalties for causing trains to run late - filling another gap identified by the audit.

The report is also critical of the fact that GO Transit inspectors looking for fare evasion are more likely to target trains outside of rush hour, with 60 per cent of inspections occurring when the trains are much less crowded.

Once caught, offenders have only a 40 per cent chance of getting a $110 fine, the rest getting off with a warning.

"Some inspectors we interviewed informed us that warnings are often issued instead of fines to avoid confrontations with riders," the report reads.

While GO says it is drafting new guidelines for train inspectors, Mr. McNeil defended GO's turnstile-free system, saying it has saved GO money in infrastructure and is more convenient for customers, most of whom, he said, pay their fare.

***

When the GO is slow

Montreal's commuter rail system beats all others in North America for promptness, but it carries only a fraction of the riders that GO Transit does.

Reasons for delays, Oct., 2006 - Feb., 2007

Weather, medical emergencies, accidents, trespassers and misc. 23%

Equipment failure* 27.4%

Resultant delays 14.3%

Congestion 14.9%

Waiting for passengers to load and unload 8.9%

Construction 12%

* Switches, signals, crossings, locomotives, coaches etc.

Initial delay results in delays to other trains.

Comparing on-time performance for North American commuter rail systems, 2006
Annual rail 2006 on-time
ridership performance
Commuter System (million) (%)
AMT Montreal 15 98
Metro North (New York) 75 97.8*
METRA (Chicago) 82 96.5*
New Jersey Transit
(New Jersey, parts of New York) 69 95.1*ø
Long Island Railroad (New York) 82 93.3*
GO Transit 41 89.5
MBTA (Boston) 38 89.0ø
SEPTA (Philadelphia) 30 88.4*ø

* Percentage of commuter trains that arrive within six minutes of the scheduled time (compared to five minutes for other systems).

Jan. to June, 2006, ø Fiscal year ending June 30, 2006.
 
GO Transit must reduce delays, collect unpaid fares
The report is also critical of the fact that GO Transit inspectors looking for fare evasion are more likely to target trains outside of rush hour, with 60 per cent of inspections occurring when the trains are much less crowded.

Once caught, offenders have only a 40 per cent chance of getting a $110 fine, the rest getting off with a warning.

"Some inspectors we interviewed informed us that warnings are often issued instead of fines to avoid confrontations with riders," the report reads.

So, if you're riding the rails for free, you're best to act like a belligerent, dangerous psychopath when the inspector arrives, so to just get a warning?

Thanks Globe and Mail!

42
 
I don't think I could take a GO train and not pay*...I mean, I'd be in an excruciating state of guilt and all these delays just make it worse.

*if I was alone...someone could convince me to tag along sans ticket, since I'm generally spineless that way.
 
I'm sorry, but isn't it the ticket enforcement people's job to confront people? That's as ridiculous as a cop saying that they don't arrest people because they want to avoid confrontation. A cook who won't go near the stove because he might get burned. A soldier who won't go into a battle zone because he might get shot at! A snow plow operator who won't plow snow because it's cold out. A coal miner who won't go underground because it's dark and scary.
 
I don't think I could take a GO train and not pay*...I mean, I'd be in an excruciating state of guilt and all these delays just make it worse.

*if I was alone...someone could convince me to tag along sans ticket, since I'm generally spineless that way.

Once upon a time, a friend of mine forgot to punch his ten ride. When we stopped at Weston, he ran out onto the platform, punched his ticket and jumped back in just as the door closed.

Guilt will make people do strange things.
 
Worse is how the consultants have taken over:

Excerpts:

• GO Transit had entered into agreements with two consortiums to manage several of its growth capital projects. In one case, GO Transit issued a request for proposals for program-management consultant services and awarded a contract worth $247,000 for the first 12 months. It subsequently extended the contract, through a series of amendments, by seven years, at an additional cost of $25 million to date.. Similarly, in the other case, it requested a proposal for 17 months' work and awarded the contract for about $2.3 million. It subsequently extended this contract for three years at an additional cost of $15.2 million to date. We noted that, in both cases, the scope of these projects, outlined in the information provided to potential bidders, clearly stated that they were multi-year projects, yet GO Transit requested bids for work spanning only 12 and 17 months. Since the capital projects under management are to continue up to 2014, the contracts with the consortiums could last for another six years without a further request for proposals.

• In another example, an information technology project initiated in December 2002 was to be completed in November 2003 at a cost of $2.4 million. By the time the system went into production in December 2006, the cost had escalated to $7.8 million. [D'oh!]

• Including the amendments to the contracts referred to above, over 60 amendments were made to contracts totalling almost $70 million, or an increase of about 75% of the original contracts' values, in the three years from 2004 through 2006. While GO Transit's Board of Directors approved most of the contract amendments put forward by management, as indicated by our interviews and review of board minutes, a number of members expressed concern over the frequency and size of the amendments but felt they had little choice other than to approve them because the projects, with their increased scope, were already well under way.

There were numerous instances of suppliers being selected without a competitive process. For example, over $8.6 million was spent on 170 consulting contracts that were single sourced in the 2004/05 and 2005/06 fiscal years.

---

• In addition, we noted a number of instances where the original cost of the consulting assignments was set at $49,500, or just below the limit of $50,000 required for a tender. These contracts were often subsequently extended, resulting in payments two to three times the original amount. For example, in June 2005, a consultant was contracted without a competitive process to serve as the acting manager of a project until a new manager was recruited. The original ceiling price of the contract was $49,500. After the new manager was hired, however, the contract was extended and the value of the assignment increased to nearly $300,000, with new responsibilities.
 
GO Transit Rail fare evasion: How prevalent is it?

Everyone: Since GO went POP in the early 90s-I remember train watching at TUS back on my 1990 trip to TO and talking to a ticket inspector who mentioned that they are never to have a predictable pattern on inspections-they can do just a few random spot checks here and there all the way to multiple inspectors doing an all-out fare blitz on a problem train.

POP took getting used to when it first started back in the 1989-90 period-I myself was used to the fare collection gates and two-half tickets. Issuing a WRITTEN warning is fine-but I am sure some of the inspectors know who the persistent fare violators are-they are the ones who are getting away with free rides while others pay their way-it definitely is NOT fair to the law-abiding riders.

I feel that GO does NOT have to literally arrest fare evaders like I have read happens sometimes on Los Angeles METROLINK commuter trains-which has a similar HONOR system-but just make fare evasion NOT worth your while-How high is the fine today on GO?
LI MIKE
 
Once upon a time, a friend of mine forgot to punch his ten ride. When we stopped at Weston, he ran out onto the platform, punched his ticket and jumped back in just as the door closed.
Living in the city, I seldom take GO - certainly not enough to do anything other than buy individual tickets.

Is there not validation machines on the trains? Seems odd that there wouldn't be ... it must create situation where one is late arriving on the platform, and has a choice between punching a ticket, and missing a train. I guess this Presto card will solve that problem.

It's kind of ironic that I don't use GO, given that I live not far from Main station, and work near Oriole station ... only 1 station in each direction from Union - but it's literally impossible to get from one to the other, with the current timetables.
 
There are no validation machines on the trains, as they are supposed to stamp the origin fare zone, which is based on the station you departed from. A smart card might help if the new readers were positioned, but if the readers were on the trains, wouldn't it have the problem of people underriding, validating their ticket after a zone boundary and chancing it a bit?
 

Back
Top