The major construction activities and associated timeline for the development are described below:
• Demolition: Completed;
• Excavation and shoring: from September 2024 to December 2024;
• Below grade formwork: from December 2025 to 07 2025;
• Above grade formwork: from July 2025 to November 2026;
• Building envelope phase: from May 2026 to February 2027, and;
• Interior finishes stage: from August 2026 to August 2027.