The major construction activities and associated timeline for the development are described below:

• Demolition: Completed;

• Excavation and shoring: from September 2024 to December 2024;

• Below grade formwork: from December 2025 to 07 2025;

• Above grade formwork: from July 2025 to November 2026;

• Building envelope phase: from May 2026 to February 2027, and;

• Interior finishes stage: from August 2026 to August 2027.
 
The major construction activities and associated timeline for the development are described below:

• Demolition: Completed;

• Excavation and shoring: from September 2024 to December 2024;

• Below grade formwork: from December 2025 to 07 2025;

• Above grade formwork: from July 2025 to November 2026;

• Building envelope phase: from May 2026 to February 2027, and;

• Interior finishes stage: from August 2026 to August 2027.
These timelines are outdated by about a year. Excavation and shoring just started recently
 