From yesterday August 23rd
Rendering looked good, so far the execution leaves much to be desired….View attachment 424987View attachment 424988View attachment 424989View attachment 424990View attachment 424991
probably glass. there are huge delays in glass right now. as seen, none of the window wall has been installed on this project yet, which at this stage would usually at least see half the building's window wall installed, or more. they may be in a position to temporarily seal the openings selectively to start unit fit-outs, but that's def not standard practiceOccupancy for this building seems to be pushed back to after July 2023. Roof has been reached. Anyone know the reasons why another 9+ months would be needed for a building like this with just 14 stories? Appreciate there were strikes by trades for a month or so in May but still.
Windows and internal unit fittings todo, what else would cause such a delay?