From this (rainy and snowy!) morning with the scaffold down.
Scaffolding moving onto the west side of the building:
June 4, 2021
Closer up view of the restored brick:
West side restoration is now mostly complete:
Scaffolding now moving on to the east side of the building:
July 24, 2021
Brick restoration work almost done. Scaffolding now on the final side at the rear of the building:
Oct 23, 2021
New windows have begun to be installed:
Nov 28, 2021
Progress on the rear (north side) of the building:
The tarp on the northside has begun to be removed.
This is one of the easier updates for me to make as I can literally see this through my home's rear windows lol
Workers redoing the east entrance: