ProjectEnd
Superstar
$21M in land, $15+M in softs, application fees, loan fees, etc., [minimum] $40M in hards, $2M contingency. [At the very least] that's almost $80M total for 70 new units without any profit (lenders won't even look at you for less than a 10% IRR and will make that threshold higher if you're unproven). Never mind whatever you may have to do to the existing building as well...