The major construction activities and associated timeline for the development are described below:• Demolition: from September 2025 to October 2025;• Excavation and shoring: from February 2025 to June 2026;• Below grade formwork: from April 2026 to August 2026;• Above grade formwork: from July 2026 to May 2027;• Building envelope phase: from September 2026 to October 2027, and;• Interior finishes stage: from January 2027 to July 2028.
I know the only product really moving on the condo side albeit slowly right now, is end user focused and I have heard that the sales on this have been moving along. I wonder if this timeline is accurate, will have to make my way out here to see if has been demolished.