I'm not a fan of these buildings. Though, technically, two towers, it appears that there are four. There is far too much monotony with respect to the design; not to mention that Southcore is already riddled with twin and triplet towers. I'd prefer to see two three distinct towers without the appendages.
 
Last edited:
Mid-February Friday

Westside Story: Work on the core continues as the interior forms have risen

173966


More steel has been delivered and is waiting on the exposed top floor waiting for installation

173967



Eastside Story: This photo at the same zoom is a matchup with the first two


173968


A closer look at the center portion of this photo shows work that has been completed on the formwork for Level 03

173971



And finally, a closer look to the northeast corner shows progress on the crash wall, extension of the wall adjacent to 18 Yonge St and forming on what will be the ceiling of the ramp from level 01 to level 02 of the bus depot

173972
 
Dear neighbours,

Below is a notice and a brief update on the progress of the CIBC SQUARE project:

Construction at 81 Bay Street
Construction continues to progress on the 81 Bay Street tower core, despite some impact from the recent snow and ice storms and extremely cold temperatures. The concrete core walls are approaching level 27, with concrete core slabs expected to reach level 21 by the end of next week. As the tower core climbs, we are installing core interior stairs on the north and south ends of the tower and have also started to install metal decking for each floor – presently installing this metal decking for levels six through nine. Work to install levels seven through nine of structural steel for the tower is well underway and expected to be complete this week. Next week, crews will proceed with structural steel installation for levels nine through 11. Setting formwork for the ceiling of level two of the new bus terminal is also underway.

Beginning Friday, February 15th, structural steel installation in the south portal and southwest retail will take place from 7 a.m. to 10 p.m., Monday to Friday. This work will take place in the areas north and south of the current core. We respect our neighbours and will endeavor to ensure that work after 7 p.m. generates limited noise, completing louder activities during normal working hours whenever possible.

Additionally, please be advised that on February 17th and 18th a small crew will be on-site to perform maintenance work. This includes work on podium tower crane number three, between the hours of 9 a.m. and 5 p.m. This crane work is being scheduled during this timeframe due to delays caused by severe weather experienced earlier this week. Crews will also be on-site to continue to secure tarps enclosing the tower core. This work is ongoing for safety, due to weather conditions. Work will begin during regular working hours on Saturday, and is expected to continue on Sunday, February 17th between 9 a.m. and 5 p.m.

Rail Corridor Overbuild Park
We continue to install structural steel in the southwest section of the overbuild park as part of the fifth phase of construction. Work in this phase includes plumbing, bolting and torqueing of steel, as well as truss installation. This phase of work is expected to continue for approximately two more weeks, weather permitting. As the final pieces of steel in this fifth phase of work are installed, you may occasionally hear increased hammering as work to fit pieces of steel together and ensure the integrity of the structure is being completed. For safety reasons, this work continues to take place overnight as workers are not permitted to be in the rail corridor during the day or evening when tracks are being used by trains. Your patience during this phase of work is very much appreciated.

When are we working?
Looking ahead, the following working hours are expected at CIBC SQUARE this week:

Hours of Work:
  • 5AM - 7AM Monday to Friday: Deliveries at 81 Bay Street, as per approved noise by-law exemption permit
  • 7AM - 7PM Monday to Friday: Regular working hours at 81 Bay
  • 7PM - 10PM Monday to Friday: Installation of steel reinforcement at 81 Bay Street and steel erection at south portal and southwest retail, as per approved noise by-law exemption permit
  • 9PM - 5AM Monday to Friday: Permitted overnight work in the rail corridor for the park overbuild
  • 9AM - 7PM Saturday: Regular working hours at 81 Bay
  • 9AM - 5PM Sunday, Feb. 17th and Monday, Feb.18th: Maintenance work on crane three

Thank you for your patience and understanding. For any questions or comments, please email us at community@CIBCSQUARE.com.
 
Those temp offices hanging off the side are a "nope-nope-nope" for me. They have to be a little bit un-nerving to work in.
 
Feb 16
Those office on the side are for the iron workers and material for them.

I see the core is starting to shrink as elevators shaft reach X floor. It starting on the south end.

More photos up on site
32198840847_0c53e6caa0_b.jpg

33265368758_6747fbdbc7_b.jpg

47140765071_7f5075b5be_b.jpg

40175870113_3e43f87888_b.jpg

40175869113_e57b1f7583_b.jpg

47140756461_a0535d0bb5_b.jpg

40175867493_0a33e05269_b.jpg

33265356348_aea81d10e2_b.jpg

33265355828_23bf4ca425_b.jpg

46226558585_1b990fca21_b.jpg

33265348778_080d994e11_b.jpg

33265346848_6d45907615_b.jpg

33265346128_e5273aeb7b_b.jpg

46226554445_001dbcce83_b.jpg
 
Of course they will be able to
 

Back
Top