A report to next's Executive Ctte seeks to update negotiations and schedules.
It does provide some info; but notes off the top negotiations were ongoing at the time the report was written and that a supplementary report will available by next week's meeting with finalized details.
Report link:
https://www.toronto.ca/legdocs/mmis/2022/ex/bgrd/backgroundfile-175184.pdf
So, that said, again, lots of info we already knew, and some matters are still in discussions, but a few tidbits emerge; from the report:
First, we learn that CF is lining up at trough for public dollars in the form of IMIT:
View attachment 375493
Second, we learn that the City wants to secure any land envisioned for employment as 'Core Employment lands' Converting only what it has to, to MCR or the like:
View attachment 375494
Third, we learn that the City has very specific phasing in mind.
Infrastructure before anything
Offices before residential
Residential-supporting infra (parks/recreation/libraries etc.) at the same time as the residential.
On the Broadview Extension:
View attachment 375495
Other matters:
The City wants an option for an elementary school here
The City wants the Soap Factory preserved in its entirely if possible and failing that, at least 2 facades
The City want a new Community Recreation Centre of size (double-pool, double-gym) They will agree to it being under a tower, but they want the CRC on the first 2 floors and it must be visually prominent.
On Affordable Housing (no resolution yet)
View attachment 375496
On Parks:
CF has apparently agreed to bump up the parks contribution and reorganize it to create a single usable park.
****
Lots more reading in the report for those who are interested.