You should check 2017 spring boards for current updates. Other than that, sit back and wait for the announcement like I am doing since we have no control over this matter. The city is willing to pay the extra cost to get things done right, even if it add time to the projects.
Good point. I forgot about the Spring 2017 display boards. They are
here and they have the updated timeline. Also, on Mississauga's main page for the project, here, there are two documents which provide updates on the procurement timeline.
The
backgrounder document says: "2017 In Summer 2017, an RFP will be issued to the shortlisted teams to prepare proposals how they will design, build, finance, operate and maintain the LRT project."
The
staff report says: "Metrolinx revised the HuLRT Project Schedule and anticipates the release of the Request for Proposals (RFP) in the summer of 2017. The RFP will include various elements such as: a Project Agreement; Project Specific Output Specifications (PSOS); and a Reference Concept Design (RCD).
In addition, a data room is being established to provide various supporting documentation for the procurement process. The procurement package will reflect the requirements for the design, build, finance, operation, and maintenance of this project, along with reflecting the recent Alstom light rail vehicle supply agreement. Mississauga staff expects to participate in relevant design briefings and commercially confidential vendor meetings as part of the procurement process but will not be directly represented on the final evaluation and selection panel.
The HuLRT Project procurement process is anticipated to be completed in summer 2018 with the financial close and contract award to the successful proponent team to follow, allowing construction to begin later in 2018. The successful proponent team is expected to complete construction and testing by the end of 2022 and will then be responsible for the operations and maintenance of the system for 30 years."