March 3
@SaugeenJunction not sure when you were shooting the area, but we miss each other. I assume you were driving, but I did the walking tour from Britannia to the 407 area as well as Kingsbridge to Robert Speck and from my place to Burnhamthorpe. Your photos are close to the 320 I took for the corridor.
I had to do some head scratching on several locations with those white on Topflight as well as the OMSF corridor. There are now two cables' between not only the white poles as well a few for the galvanize ones as well and they have a turning bracket in the centre of cable. The rest of the galvanized poles have a bracket on them for a single track.
I thought the OMSF trackwork was 100% done, but there is a section where the track curves to the east that is missing concrete for the track. There also two more areas waiting for poles and wires in place of brackets as they will be further away than the others one for some odd reason.
The guideway from Topflight to the crossover area has seen two of the six curbs pour it with the southbound track area being prepared for the concrete base.
Derry station has seen no work since I saw it a week ago with the top flashing missing and nothing on the east panel like the west side.
Over a dozen white poles missing from the 401 to Topflight and a number of those poles that are up are missing brackets.
When I compare today's visit to last week as well for Jan and Feb, that has seen truly slight changes for this year so far. We may see all the trackwork from Topflight to Matheson in place and pour by May. From Bristol to Eglinton could be June or July depending on the manpower that shows up shortly.
On thing I noticed today, they are pouring the topcoat of concrete for the future station at Skyway Dr.
The other thing I noticed was the amount of splicing that still must be done for the rails already in place as well as how they plan to deal with expansion joints. Where splicing is to take place, there is a C Clamp holding steel plates on both sides of the area. The expansion joint has a steel bar on both sides of the gap and held in place where the rail clips are.
No trackwork has started for the Hwy 401 bridge, but concrete repairs are taking place for the bridge deck. Only a small section to see concrete for the section from the Hwy 401 eastbound off ramp to Britannia as the rest of that area is complete.
Still no trackwork or station form and pour for the Britannia south block.
Concrete curb is to be poured this week for the northbound lane from the Hwy 403 off ramp to Ellia that will then see milling of the road to pave the northbound lane. Once this is done, traffic will be switched to it to allow building the guideway across the intersection this month with a partial closure for it. Left turns here will be a major issue as it affects two bus routes and forcing long detours for the area.
Robert Speck intersection should see a shift of traffic to the north side since that area is totally completed to start work on the south section this week.
Matthew Gates is closed, and very little work has taken place this past week.
Photos will follow sometime this month as I am still work on Feb 25 photos with March 1 to follow them