April 13
One needs to take dates as to when things will be completed or started with a grain of salt as the record of accomplishment is extremely poor for them these days let alone the past year.
Queensway intersection was to see guideway construction Jan 8 to the point miWay had buses on detour for that day and it was canceled as the intersection wasn't ready that day nor is at this time. That date was given in early Dec.
Both Robert Speck and Matthew Gates intersections were closed a week later than announced along with signage.
Topflight open up at the end of January that the plan early Oct date.
Elm Dr was to be closed April 3rd with notices up for 2 weeks in advance only to have it canceled April 1. It ended up taking place April 8 with residents receiving a notice for it days after it was closed, including me. The intersection is ready for the base to be poured this coming week.
It was show in a photo above that the crosswalk was missing for Matthrew Gates intersection that now has a temporary asphalt walkway in place of a concrete on like all the rest that has been done to date for some unknown reason.
It was noted Absolute intersection was to be closed in the first 3 months of this year and I expected it to happen after Robert Speck was reopened fully. Crew was working on Absolute intersection today that was closed on April 9 to May 7 according to the notice on Hurontario St.
I expect Square One Dr will be next that will take 2 months to do and cause some traffic issues.
Burnhamthorpe is an T connection like Topflight, but opposit hand that it will have to be built in 3 phases over a course of 3-4 months if they don't do the same screw up like Topflight.
The south pier of the Hwy 403 bridge is still the same as I shot it on March 28. The north pier base and the major slab to the north of it will be poured this week with the rebar in place for some sort of support from the pier. I expect this will be a transition support base from the bridge to the Styrofoam base for the ramp to connect to Hurontario St at the 403 off ramp location. Looks like the support will be a T shape.
Looks like the last section of the north retaining wall for the Rathburn ramp has been poured.
I was planning to look at the corridor today, but other things came up.
All the photos from March 28 to today are now online.
Elm Dr
Matthrew Gates
Absolute Intersection
Part 2 next