Oct 2/3
The Exchange Tower is where an office tower used to be that was out dated and 50% empty.OMERS whas down size and cancel office towers for their land. There is a lot of empty land east of Dixie road on both side of Eglinton that will draw office towers there first than MCC. Sames goes for the airport area. There are a few office towers that will match the flight height restrictions along Hurontario north of Matheson. There are other areas that still can built office towers that will be cheaper to rent than MCC and until they are max out, Office towers will be a long time coming to MCC with 15-25s being the tallest they will be unless part of residential toweres which should happen in the first place.
What a week that has seen a lot of changes for the corridor. Was planning to take some photos shots of Central Pkwy on my way home and after doing some shopping on Friday but late doing so that only got a few shots due to poor lighting. Counted over 2 dozen workers finishing work on more poured concrete for the northbound track with a lot sitting around waiting for something to happem. About 2 hours after doing shopping, most were still there in the dark sitting around.
Shot the area around 8am and still on the darkside as the sun was rising that saw over a dozen workers on site doing various things, A lot of concrete grinding was taking place with hand grinders and haven't seen this after concrete was poured for tracks. The southbound track was being prepared for concrete pour next week. Noticed 2 areas of hydro work taking place with one pole being held in place.
Once the concrete work is finished for CP-Fairviw area, they will move to the Fairview-CPKC bridge area.
What got me the most was Cooksville Station as the base has been poured for as well forming for the guideway base including the northside of CPKC bridge area that is now ready for concrete. I knew last week the station guidway would be pour as there was no sign of form work for the station.
Steel Mats are being place from Agnes to Hillcrest for the southbound track with some ties in place. There is a stock pile of rails on site wil rail place along the guideway for this area.
The Queensway station platform is now poured.
Had a look at the Hydro work for the North Service Road area. New poles along with wiring has been installed over Hurontario and further back from it as well poles to deal with the poles that need to be remove from the southbound curb lane, Those curb lane poles has the wires removed from them as well cut down at the top considering these are concrete poles in the first place. To the north of the plaza, new poles in place as well strung with 2 poles taking the line to an underground duct work to the North Service Rd poles. Communication cables needs to be remove from the poles that will be remove hopeful this year.
Hydro duct banks being installed south of King St on the westside now.
All photos on line
CP-Fairview
Cooksville Station
Queensway Station
North Service Rd
The 2 poles with cables going underground
Agnes To Hillcrest