A naive question : is this a City bluff to force Conservatory Group to go ahead with their development ?Since this Conservatory Group Ruby development application is technically dead - but they're still holding up Beecroft North Extension,... I'll be squatting Beecroft North Extension here (as I've been squatting Doris South Extension at 55 Sheppard East thread)
Since Conservatory Group (Yolanda Flanders) don't have active development application here,.... City can't get conveyed land for Beecroft North Extension at this Inez Court site.
--- So instead of extending Beecroft Road directly north to Drewry, Beecroft Rd will become at east-west road to cross Yonge at NorthYorkHydro (Times Group 5800 Yonge) site to form J-Road to connect with Cummer hence "Beecroft Extension to at least Turnberry Court to connect to Cummer Ave (2024-2026)" which coincide with completion of Aoyuan's M2M Phase 1 & 2 at former NewtonBrook Plaza site. Based on Development Applications - by 2026, there should be 10 new condo towers completed here along Yonge south of Drewry/Cummer to J-road (Aoyuan's M2M, Times Group 5800 Yonge, 5840 Yonge); about 4,000 additional new condo units,... IE 4,000 additional cars! (I'm not even including north of Drewry/Cummer! Ghods', North Yonge St, 905er side of Steeles, etc,..)
View attachment 291818
Yellow line shows "Beecroft North Extension" City committed to in funding.
Construction Phasing Strategy
• Phase 1 - Doris Ave Connection to Tradewind Ave Extension (2023-2024) - Fund in Reserve Fund due to lateness
• Phase 2 - Beecroft Extension to at least Turnberry Court to connect to Cummer Ave - Funded
(2024-2026)
• Phase 3 – “Transform Yonge” (2026+) - UnFunded
Pg 16: https://www.toronto.ca/legdocs/mmis/2020/ie/bgrd/backgroundfile-158594.pdf
Beecroft North Extension (Finch Ave to Drewry/Cummer):
- Timeline: 2024-2026
- Already Funded: Beecroft Extension north to Drewry Ave by 2024 ($10.892m) & 2025-2029 ($17.726m) ***
Top of pg 31: https://www.toronto.ca/legdocs/mmis/2020/bu/bgrd/backgroundfile-141484.pdf
- Notice, budget has 5-year 2025-2029 ($17.726m) that may go beyond this stated 2024-2026 timeline. WHY? Because, City doen't own all the land required for Beecroft North Extension! Same issue City had and Still Have for Doris South Extension!
- City still need 3 chunk of land - Inez Court, north side of HendonAve & westside Greenview Ave
Notice how that J-road from TimesGroup 5800 Yonge to Aoyuan's M2M link up to the purple mid-block proposal for Doris North extension that Cllr Filion is proposing - to save his favoured Silverview Community (meandering roads east of Yonge between Finch Hydro Corridor and Cummer) VS Dumont Rd City Planning favours which cut through Silverview Community
View attachment 291819
pg 20: https://www.toronto.ca/wp-content/u...nity-Consultation-Meeting-October-29-2020.pdf
If this J-Road is built, City wouldn't need that piece of land and can play really hard ball.