November 18 Afternoon. Installation of the cladding / glazing units along the ground floor of the building's entire King Street facade is now complete. The centre section of the King Street frontage consists of heritage structure facades that were retained in place, so will only need new glass in the existing building window openings.

Installation of the cladding is proceeding along the east wall of the opening to the courtyard. Once installation wraps around the courtyard all that will be left to be done for the ground floor will be the south east section of the courtyard wall, including the wrap around the back to where the heritage building has been retained. Then we should see installation activities starting on the Second Floor.

Heading south into the courtyard:

View attachment 613140

Interior courtyard ground floor areas still to be done. New glazing visible at the left edge of the photo immediately below.





A lot of cladding / glazing sections on site and ready for installation

View attachment 613141

I didn't go to the presentations they held when they had the sample walls up but are the corners supposed to be sort of unfinished and exposed? Are they going to add an additional piece?
 
So Nov 2025?
August 2026 seems reasonable at this point.
We shall see. I would be surprised if the envelope is wrapped up by the end of 2025, but that is just my opinion.
The ground has been going on for 6 weeks, I think. The floor plate for this is very large. It will likely take multiple weeks to complete each level, and there are 16 stories.
That also assumes production of the balance of the curtain wall is on track, and can keep up.
 
I didn't go to the presentations they held when they had the sample walls up but are the corners supposed to be sort of unfinished and exposed? Are they going to add an additional piece?
almost certainly. aside from aesthetic reasons, leaving it exposed is a massive waterproofing and air tightness issue.
 
I didn't go to the presentations they held when they had the sample walls up but are the corners supposed to be sort of unfinished and exposed? Are they going to add an additional piece?
Based on the pictures from that event - they'll get an additional fill in piece at the corners:
1732112850050.png


Source is UT story :)
 
November 20 - Installation of the ground floor cladding and glazing has progressed down the east side of the courtyard entrance from King Street and wrapped around to the north side of the courtyard's east section. Footings for the cladding sections are being installed on the south side of the courtyard's east section and along the return to the heritage 495 King Street West building in the south-east corner of the King Toronto project.

East side of courtyard entrance, from King Street down to the main courtyard area:

20241120_122702.jpg


King Street frontage:

20241120_122724.jpg


Courtyard north-east wall seen from the south (Wellington Street) side:

20241120_124205.jpg


Footings along the south east side of the courtyard. Once this last section is finished, that should complete installation of the entire ground floor main cladding and glazing sections. (Some of the installed sections are lacking vision glass pieces, to be installed later.

20241120_124242.jpg


20241120_124221.jpg
 
Last edited:
We shall see. I would be surprised if the envelope is wrapped up by the end of 2025, but that is just my opinion.
The ground has been going on for 6 weeks, I think. The floor plate for this is very large. It will likely take multiple weeks to complete each level, and there are 16 stories.
That also assumes production of the balance of the curtain wall is on track, and can keep up.
Correct me if I'm wrong, but the initial occupancy date, doesn't mean the building is 100% finished.
Most buildings are still being worked on while people move in during the occupancy phase.
So I think a summer 2026 date seems reasonable, unless something derails the project.
 
Correct me if I'm wrong, but the initial occupancy date, doesn't mean the building is 100% finished.
Most buildings are still being worked on while people move in during the occupancy phase.
So I think a summer 2026 date seems reasonable, unless something derails the project.
That is true, but keep in mind that none of the upper floors (i.e. L4 up) have been assembled and are ready to ship to site. That is a major potential risk to Summer 2026.
 
Based on the pictures from that event - they'll get an additional fill in piece at the corners:
View attachment 613549

Source is UT story :)
Correct. The corner is one piece not split so must be field installed. To pre-install it would require the corner curtain-wall to be a pre assembled corner frame, which would be incredibly heavy and unwieldy.
 
Since the glass square cladding has started going up, I've really been noticing how much of this stuff already exists (usually in little bits) in different parts of the city.

A little bit at Broadview and Gerrard:
1732129622046.png


Bathurst and Dundas:
1732129684746.png


Dupont and Ossington:
1732129842096.png


St. Clair and Dufferin:
1732129927054.png


And many more places! It's funny how one project can open your eye up to these little details elsewhere.
 
Since the glass square cladding has started going up, I've really been noticing how much of this stuff already exists (usually in little bits) in different parts of the city.

A little bit at Broadview and Gerrard:
View attachment 613673

Bathurst and Dundas:
View attachment 613674

Dupont and Ossington:
View attachment 613675

St. Clair and Dufferin:
View attachment 613676

And many more places! It's funny how one project can open your eye up to these little details elsewhere.
wasn't it super popular in the 80s/early 90s? I've seen tons of homes with it as well
 
Since the glass square cladding has started going up, I've really been noticing how much of this stuff already exists (usually in little bits) in different parts of the city.

A little bit at Broadview and Gerrard:
View attachment 613673

Bathurst and Dundas:
View attachment 613674

Dupont and Ossington:
View attachment 613675

St. Clair and Dufferin:
View attachment 613676

And many more places! It's funny how one project can open your eye up to these little details elsewhere.

Heritage facade on the Nobu building has them too
 
Yeah, I just picked a few that were fresh in my mind, but they really are everywhere. I think the vintage is '70s more than '80s/'90s? When I was a kid, one of my aunts and uncles had a *very* '70s styled house that had a bunch of this.
 

Back
Top