Here is an update on the Bascule Bridge work that was recently posted by PortsToronto. See:
https://www.portstoronto.com/portstoronto/media-room/feature-stories/port-of-toronto-ship-channel-bridge-–-rehabilitati.aspx
They were tidying up the east sidewalks around the bridge last week and the bridge is now fully open to vehicle traffic.
"This project will modernize three key components of this ageing infrastructure. Phase 1 of the Ship Channel Bridge Rehabilitation Project will reach substantial completion in March 2024, and as a result, both the north and south roadway approaches to the bridge will re-open to vehicle traffic in early February 2024.
Phase 1 – Substantial completion in March 2024.
- Rehabilitation of the bridge north and south roadway approach spans.
Phase 2 – To commence in late 2024.
- Restoration of the Bascule lift bridge structure.
- Replacement of end of life mechanical and electrical lift systems.
The majority of work related to this phase of the project is limited to the winter months when the Ship Channel Bridge lift is not operational. It is expected that the overall project will be completed in 2027.
During this project , PortsToronto and the City of Toronto will ensure the continued safe transportation of cargo and goods across the Ship Channel Lift Bridge while maintaining marine, vehicle and pedestrian traffic along the various rights of way serviced by the bridge.
PortsToronto consults with the Mississaugas of the Credit First Nation on all projects.
For project related enquiries, please contact shipchannelbridge@portstoronto.com.