Some more shots from 10/21/16. Almost at ground level now, maybe one or two more levels of underground parking to go.
![30462156845_5dc2ff5bfc_h.jpg](https://c2.staticflickr.com/6/5650/30462156845_5dc2ff5bfc_h.jpg)
![30462159035_b2446931dd_h.jpg](https://c2.staticflickr.com/6/5808/30462159035_b2446931dd_h.jpg)
15 months to occupancy looks unlikely. More likely later 2018 by my guess, they are still working on parking levels. Topping out is probably July, with occupancy October to December sometime.