Stop by the site today for T3 and nothing worth shooting. Still 2-4 weeks before the hole is completely dug out and no other work has stated in the hole.
 
April 2nd
1680998986527.jpeg
 
Thanks for the update. Btw I saw a Statistics Canada report that gave the populations of secondary downtowns in Canada and Mississauga Centre was around 65 000. If I’m not mistaken that would make it one of the larger centres in the country and the opening of all of these towers over the last few years will only push it further up. I hope that the city is planning for the appropriate facilities. I can’t think of an American metro that has such a large secondary downtown as well as a healthy dominant core.
 
April 21 & 24
More up on my site.

They are back at digging the hole out again and could be completed this month.
52869107416_687766e8e5_b.jpg

52869490815_ce5dd6f58a_b.jpg

52869276749_95233ab764_b.jpg

52868623470_7ce8211e1e_b.jpg

52868623580_0354afb01d_b.jpg

52867668832_e0fc4af663_b.jpg

52868679368_8c72a3eedb_b.jpg
 
May 10
One way or another the hole will be fully dug out my the end of the month. They were still jackhammer the north west corner and digging it out well shooting it.
52901345206_2353691cbd_b.jpg

52901505714_325c2d6c91_b.jpg

52901793453_1ecf13204f_b.jpg

52900774197_d198aec61a_b.jpg
 
May 26
Well the person running this project is off a month having the hole dug out by the end of this month from what he told me a few weeks ago.

Shooting the south end clearly shows about 25% of the hole to to be dug that is about 18 feet high of bed rock.
52928629225_d02c475134_b.jpg

52928249451_388d6c227a_b.jpg

52928690408_71821a1ce7_b.jpg

52927661842_3fd9e03c77_b.jpg
 