The (very slow) ascent skyward...

PXL_20240302_174206472.jpg
PXL_20240302_174210681.jpg
PXL_20240302_180754054.jpg
PXL_20240302_194849913.jpg
PXL_20240302_194924128.jpg
PXL_20240302_195204155.jpg
 
They finished level 16 floor on Feb 27. It should be less than 2 weeks for this level, then a straight run from Level 17 - 104/105
31,56 & 81 have smaller mech rooms and the west elevator stops at 56 with storage for 20 floors above that in the core with the same forms.

From the site plan approval drawings of Oct 2022.
IMG_6018.jpeg


Friday March 8
IMG_0185.jpeg
 
They finished level 16 floor on Feb 27. It should be less than 2 weeks for this level, then a straight run from Level 17 - 104/105
31,56 & 81 have smaller mech rooms and the west elevator stops at 56 with storage for 20 floors above that in the core with the same forms.

From the site plan approval drawings of Oct 2022.
View attachment 546728

Friday March 8
View attachment 546729
So the west elevators start stopping at the 13th floor, I imagine? In other words, the hotel has its own lifts?
 