I ended up walking from Bay To Bathurst today considering I was only planing on the section west of Spadina.
From Bathurst to Dan Lackie Way, Concrete sidewalk and pave MGT only with work taking place. A layover bay is being built there and should be finish well before June 19.
From Dan Lackie Way to Yo-Yo Ma Lane, concrete sidewalk and pave MGT finish, other than markings.
From Yo-Yo Ma Lane to Spadina, the eastbound lane is finish for traffic. The MGT from this point east is the same as the rest of the south side and far from finish. This also applies all the way east to Ress. Barriers are to be place over the bridge between TTC ROW and the MGT.
The south side is clean from Bay to Simcoe, with some stone work to be done at York. Paving should be done this week for the MGT up to Ress. Ress is still a mess.
With 3 weeks to go, going to be tight on a few things, but will not be 100% complete by June 19 to stop the official opening and the return to eastbound traffic.
Had to stop an US driver from making a U-turn at the EMS, so he could use TTC ROW to go east.
People were like deers caught in the headlights of cars when they saw the streetcars coming at them, with drivers laying on the horns and bells. A few driver fail to make their green light because of these deer looking people.
I expect once the fences come down, people will be crossing all over the place. Will be fun to see what the cyclists do with these deer looking people once they have control of the MGT. A few places missing lights for the MGT, but should be up this week.
Bay intersection still needs the curbs this week so final paving can get underway for it as well moving west.