How long is B+K going to be shutdown?
King Streetcars are to start running on Wed with parts of Bathurst on Thursday.
The intersection is to be plane on Monday and pave on Tuesday.
For rebuilding a full Grand Junction, not bad for 2 weeks of work. Hydro is the hold up as they finally finishing their work this weekend to allow the rebuilding of the road, curbs and sidewalks.
The new 2.4m platform still has be be built for the northbound one that was too narrow and short for the new cars. There was talk about a southbound being built considering they wasn't one there before nor indication of so at this time. Time will tell if it does get built.