However, there will also be a slowdown as they get to the top of the hotel suite floors and then construct the various hotel spa, residential skylobby and mid-rise mechanical room floors.
The higher up they go the longer it takes to carry materials up so that will slow things down. Lifting stuff by crane 700 feet up takes longer than lifting something 100 feet.