I'm sorry for taking this off-topic but this statement is completely untrue - the subdivision land acquisition and approvals/development process takes far longer than the high-rise process - about a decade in fact.
Let me very briefly walk you through...
- Preliminary Planning Review
- Phase I Environmental Site Assessment
- Preliminary Engineering Review
- Property Purchased by Developmer
- Pre-consultation with municipal planning staff
- Assembly of existing plans, reports & surveys including: archeological survey, environmental impact study, traffic study, noise study, geotechnical study, topographical survey / vegetation study, stormwater management / erosion control stiudy
- Preliminary engineering design
- Search registry office / boundary survey
- Calculation & Drafting of Plan
- Preparation of Draft Plan of Subdivision & Association Planning Documentation
- Submission of Draft Plan Rezoning Application (Official Plan Amendment as well if necessary)
- Submission of Draft Plan with prescribed & other info as provided by Official Plan Policy
- Circulation of Draft Plan to Local Municipality & Regional, Provincial & Federal Agencies
- Submission of Survey's certificate & application to property law program for registration in land titles office
- submission of Plan to Land Boundaries Program & Registration to surveyor
- Report by Municipal Planning Staff
- Public Meeting by Local and/or Regional Council
- Council approval of Draft Plan / or refusal / or approval with conditions
- Official Plan / Zoning Amendment (potentially with conditions)
- Notice of Adoption
- Potential Appeals to OMB (this step alone could take a couple years)
- Draft Plan Approval and Conditions of Draft Approval Issued
- Official Plan Amendment / Zoning By-Laws come into force
- Approval from land boundaries process & registration in land titles system
- Preparation of subdivision agreement and/or front ending agreement
- Preparation of conceptual municipal engineering design
- Preparation of subdivision agreement schedules
- Preparation at final engineering drawings
- Review of engineering designs by municipality & region
- Approval of Ministry of Environment Applications
- Preparation of landscape design & review process
- Utility design, engineering & approvals (gas, cable, phone, electrical)
- Circulation of Final Plan of Subdivision
- Monumentation of Final Plan
- Final Plan to Registry Office & Approval
- Subdivision Agreement Approved by Council
- Development securities to municipality & letter of release
- Clearing of Draft conditions
- Letters of release by commenting agencies & approval authorities
- Approval by Approval authority for registration of plan & final plan of subdivision
- Registration of the Plan of Subdivision in the Land Titles Office
- Provincial Ministry & agency approval of engineering design
- Preparation of specifications and tendering documents / call for tenders
- Preparation of electrical & utility tenders
- Installation of electrical services, lighting, cable & bell
- Construction of base municipal services
- Preliminary acceptance of underground services
- Submission of site plans and building permit applications
- Development Charges Payment
- Permits Issued
- Construction of balance of municipal services & municipal acceptance of above ground services
- Building (homes) construction
- Occupancy Permits Issued
- Final acceptance of municipal services
- Assumption of services by council & release of balance of development securities
The generalized road map does not even include Master Environmental Servicing Plans, Conservation Authority approvals, Ministry of Environment or Ministry of Natural Resources Approvals. Sorry for the long sidebar not about Teahouse - but please don't tell me subdivisions "just pop-up" as the approval process can take over a decade (far longer than condo approval process)